DBA had the great fortune to be working with the Alabama Department of Transportation (ALDOT) on a very interesting bridge project in Lacey’s Spring, Alabama just south of Huntsville, Alabama. On February 12 and 13, 2020 a large landslide occurred on SR-53 (US-231) at milepost 301.7 in Morgan County approximately 1.7 miles south of the Laceys Spring Community. The slide completely severed the 4-lane divided highway which is a major commuting route between Huntsville and several communities south of the city. Many of the workers at the U.S. Army Redstone Arsenal, NASA Marshall Space Flight Center, and the contractors and vendors that support these two major installations live in the communities impacted by the closure of the highway. Detours were established on existing state and county roads, but these added 30 to 60 minutes to commute times, depending on time of day. ALDOT was under significant pressure from the impacted communities to quickly solve the problem and reopen the road.
ALDOT drilling crews were immediately mobilized to the site to begin drilling exploratory borings and install slope inclinometer casings for monitoring slide movements. The Department of Civil Engineering at Auburn University was engaged to perform geophysical testing in conjunction with an existing research project for ALDOT. Geotechnical engineering firm TTL also assisted with field investigation efforts.
DBA and ALDOT immediately began evaluating several alternate concepts for stabilizing the slide and reopening the road during the soil and rock exploratory drilling. The design team looked at several retaining wall options, a complete rebuild of the roadway, and bridges. ALDOT selected a solution that removed most of the existing roadway embankments (built in 1947 and 1970) to reduce loading on the slope and then spanning the slide area with bridges built on the existing road alignments, with the bridges designed to withstand future movements of the slope. Excavation was begun by Reed Contracting before bridge design was complete in order for the rough grading to be done before the bridge contractor mobilized.
The bridges are two-lane structures, one Northbound and one Southbound, each about 947 ft in length. The superstructure is AASHTO BT-72 concrete girders and a concrete deck. There are seven spans in each bridge each about 135ft long. The grading work was begun while the bridge was still being designed to accelerate the schedule and shorten the time the road would be closed.
The foundations for each pier are a pair of 9.5ft diameter, permanently cased drilled shafts with 9ft diameter rock sockets. The sockets are 14ft long into the limestone and shale bedrock. The limestone uniaxial compressive strengths range from 10,820 psi to 28,100 psi.
After much design and analysis in a highly compressed schedule, a bridge contract was let for bid in early May 2020, less than 3 months after the slide occurred. Brasfield & Gorrie was the successful bidder and awarded a $15 million contract that has incentives for finishing early, and disincentives for finishing late.
ALDOT UAV flight June 16, 2020
ALDOT UAV flight July 07, 2020
ALDOT UAV flight July 23, 2020
ALDOT UAV flight July 28, 2020
ALDOT UAV Flight Aug 08, 2020
ALDOT UAV Flight Sep 2, 2020
ALDOT UAV Flight Sep 15, 2020
A.H. Beck (Beck) was the drilled shaft contractor, drilling each shaft, placing reinforcement, and placing concrete. The 9.5ft diameter permanent casing is 5/8 inch wall thickness spiral weld 60ksi steel fabricated by Nucor in Birmingham, Alabama. The shafts are reinforced with a 1.5inch wall thickness, 8ft diameter, 60ksi steel pipe. These pipes were rolled and welded by Favor Steel in Birmingham, Alabama before being trucked to the site. The steel plate was manufactured by SSAB in Axis, Alabama near Mobile. So, the structural steel pipes were completely Alabama-made and the steel travel almost the length of the state!
The pair of shafts for each pier is connected by a reinforced concrete grade beam 10ft wide by 7ft high by 46ft long. To connect the shafts to the grade beam, a 14ft long reinforcement cage is placed in each shaft, embedded 8ft into the shaft with 6ft embedded in the grade beam. The cage consists of 28 No.18 Grade 75 bars.
The project includes a robust instrumentation plan with ShapeArray inclinometers installed in each shaft and in the slope, supplemented by traditional inclinometers in the slope and vibrating piezometers to monitor groundwater levels. DBA and ALDOT will monitor the bridge and slope, intending to be able to measure displacement and calculate strain and loads in the shafts should the slope move again in the future.
Foundations were completed a few days ahead of schedule at the end of July 2020. The deadline to have the bridge open to traffic was early December, 2020, but Brasfield and Gorrie had an aggressive plan to complete the project early and earn the bonus for early completion. The bridge was open to traffic September 28, 2021 to much rejoicing among the commuters and others that use this route. Volkert was the CE&I Consultant on the project for ALDOT, providing construction management and inspection services for the project, ensuring all requirements were met to build the bridges.
To read more in detail about the design and construction of the bridge foundations, we published an article i nthe April 2021 issue of Foundation Drilling Magazine:
Click HERE for some of the photos DBA team members have taken during construction.
To see aerial views from ALDOT’s UAV flight taken on July 10, 2020, click HERE.