kcICON River Bridge Update

Work is well underway on the main pylon foundation for the Christopher S. Bond Bridge on the kcICON project in Kansas City. By Labor Day, 4 of the 8 shafts (with 10.5-foot diameter rock sockets) will be completed. Construction of the shafts is progressing smoothly. The Pylon shafts may be completed as early as the end of September. Work on the land shafts will start sometime after Labor Day.

The photos in the slide show below were provided courtesy of the Missouri Department of Transportation (MoDOT).

Update: MoDOT has set up a webcam on the exisiting bridge looking down on the pylon construction. Check it out here.


Technorati : , , , , ,

Progress at Audubon Bridge

jja-west-pier-view-from-water-080813_3.jpg

Audubon Bridge Constructors (ABC) is making progress on the new John Jame Audubon Bridge near New Roads and St. Francisville, Louisiana. Steve has been spending quite a bit of time there looking at shaft excavations ,test shaft installations, and test pile installations. Paul made a trip in July and I made one earlier this month to give Steve a break. It is really amazing to be part of such a large bridge project. The amount of work required to build the foundations is incredible. I have posted a couple of slide shows below from the visits Paul and I made. Links to the slide shows and albums are on the project page.

Shafts W21 and W 5 – July 2008

 

Shaft W12 and West High Approach Test Shaft – August 2008


Technorati : , , , , , , , ,

kcICON Moving Forward – Test Shaft Installation

DSCN2673_s.jpg

I have been slow in posting on the progress of our part in the kcICON project (see here for background and here for latest project images by MoDOT). The exploratory drilling went very well with a short pause due to ice in the river in late January. The crews from Terracon did an outstanding job getting the borings completed, overcoming the occasional problems with drilling tools deciding they did not want to come out of the hole.

DSCN0528_s.jpg

Design work by Parsons on the main bridge proceeded (and is still ongoing) through the rest of winter and into the spring. In late April, PCC installed the test shaft in the middle of the pylon foundation with a 6-foot diameter rock socket 20 feet long. The shaft was tested using a group of 3 O-cells placed near the bottom of the shaft. The test yielded excellent results in both side shear and end bearing in the shale socket. Look for us to include the results in a future technical paper or journal article.

Design is continuing with the pylon shafts anticipated to be started in early July. The abutments and approach piers are schedule to be started later this summer or early fall.

The slide show embedded below has some photos of the exploratory drilling and the test shaft installation. Enjoy!


Technorati : , , , , , , ,

ADSC 2008 Faculty Workshop Field Day at DBA

ADSC 08 FacWkshp 23.jpg

Well, the ADSC 2008 Faculty Workshop Field Day was a great success! A group of 46 civil engineering faculty members from across the country participated in the week-long workshop that culminated in a field demonstration day at the World Headquarters of Dan Brown and Associates in Sequatchie, Tennessee. The participants and instructors were treated to installation and testing demonstrations of drilled shaft foundations, micropile foundations, and anchored earth retention systems. The load tests included a static load test of a micropile and a Statnamic test of a drilled shaft, which provided some of the day’s excitement. Installation demonstrations of the various drilled foundations and anchors allowed the participants to observe how the various elements are installed. Even though we had to dodge an occasional thundershower, everyone had a great time and felt that they went away with a lot of valuable information for their classes back home.

More info on the Workshop here.

I put together a slide show of photos taken by myself (Robert) and Dr. Erik Lohr.


Technorati : , , , , , , ,

DBA HQ site of ADSC Foundation Engineering Faculty Workshop Field Demo

DBA will be hosting the field demonstration day for the ADSC Foundation Engineering Faculty Workshop on Friday, June 13th. Long Foundation and Hayward Baker have installed examples of several foundation and retaining structures, including drilled shafts, micropiles, and soil nails. During the field day demonstrations, the attendees will observe additional installations, load tests, and non-destructive testing. The activities are all being held on the grounds of the Trials Training Center (Dan’s “hobby”) in scenic Sequatchie, Tennessee, which is also the location of the DBA Corporate Office (or as we like to call it: DBA World HQ). Dan took the photos below of Long Foundation and Hayward Baker at work getting ready for the demonstration day. You can see the TTC lodge in the background of some of the pics.

HB mpile_s.jpg HB nails1_s.jpg

HB installing micropiles (L) and HB installing soil nails (R)

HB wall_s.jpg Long1_s.jpg

Tieback retaining wall (L) and Long Foundation drilling a shaft (R)

Some info on the workshop from ADSC:

The Workshop offers classroom and field work. It will provide the participants with all the tools needed to teach the fundamentals of drilled shaft and anchored earth retention design for foundation engineering studies at the undergraduate and graduate level. The program focus will be on drilled shafts, anchors, and micropiles. In addition to the classroom experience attendees will participate in hands-on field demonstrations of the latest construction and testing techniques. Each participant will be provided with a complete take-home Teaching Package including texts, manuals, and audio visual aids all in electronic format..

A list of the workshop faculty, composed of many experts in the field of geotechnical engineering and construction:

Lead presenters are top experts in the fields of deep foundation and earth retention design and construction. In addition to Dr. Brown the teaching faculty includes Dr. John Turner P.E., University of Wyoming, Dr. Jim Long, P.E., University of Illinois, Dr. Dave Weatherby, P.E., Schnabel Foundation, Dr. Don Bruce, P.E., Geosystems, Inc., Dr. Eric Loehr, P.E., University of Missouri, as well as Allen Cadden, P.E., Schnabel Engineering, Jerry DiMaggio, P.E., FHWA, Alan Macnab, P.Eng., Condon-Johnson& Associates, Tom Armour, P.E., DBM Contractors; Dr. Tom Witherspoon, P.E., S&W Foundation, John Wolosick, P.E., Hayward Baker, and many other deep foundation academicians and practitioners.

We’ll have more after the workshop.


Technorati : , , , , , , , , , , ,

Welcome to newest DBA team member, Paul Axtell!

DBA is proud to announce the newest addition to the team – Paul J. Axtell, P.E.! Paul comes to us from the U.S. Army Corps of Engineers Kansas City District office. He received his B.S. in Civil Engineering from the University of Missouri-Columbia and his M.S in Civil Engineering from the University of Texas. Paul’s geotechnical engineering experience includes slope analysis, ground improvement, dam engineering ,and deep foundations. One of Paul’s first projects will be the kcICON project in Kansas City. Paul’s resume is now available on the About Us page of our site.

Welcome aboard, Paul!

axtell1a.jpg


Technorati :

Slope Stabilization Method with Micropiles – A report for the ADSC/DFI Joint Micropile Committee

Erik and Dan have published a final report entitled “A Method for Predicting Mobilization Resistance for Micropiles Used in Slope Stabilization Applications”. The report was prepared for the Joint ADSC/DFI Micropile Committee. This version has been submitted to the committee for review and comment. From the report:

The primary objective of the work described in this report has been to identify a method for predicting the resistance provided by micropiles used for slope stabilization that: (1) is consistent with the available field performance data, and (2) takes advantage of the improved knowledge gained from the performance observed in previous implementations. This objective has been met through review and analysis of case histories with well documented performance measurements, analysis of stability and load transfer for these case histories, development of an improved technique for predicting the resistance provided by micropiles, evaluation of the proposed technique as compared to available field performance measurements, and, finally, use of the technique to demonstrate its application for a hypothetical case and to demonstrate the implications of the technique for design of slope stabilization schemes with micropiles.

This report should be a great resource to practicing geotechnical engineers considering micropiles for slope stabilization.

Financial support for this work was provided by a grant from the H.B. Williams Industry Advancement Fund of ADSC: The International Association of Foundation Drilling.

A copy of the report can be downloaded here.


Technorati : , ,

JJA Bridge in ENR.com article

An article entitled “Historic Cable-Stayed Link Taking Shape in Louisiana” about the construction of the John James Audubon (JJA) Bridge in Louisiana is on ENR.com here. The drilled shafts actually extend much deeper than indicated in the article, for what its worth. I think they were only talking about the permanent casing, not the entire drilled shaft.


Technorati : , , , , , ,

Lateral load tests of drilled shafts behind an MSE wall – research with KDOT and KU

header_title.jpg

DBA is part of a research project involving laterally loaded drilled shafts and MSE walls with the Kansas Department of Transportation (KDOT) and the University of Kansas. The ultimate goal of the study is to develop rational design procedures for situations where drilled shafts are constructed near or adjacent to MSE walls. From the study proposal:


Drilled shafts used to support sound walls and other structures are often constructed near the facing of mechanically stabilized earth walls (MSE walls) due to right-of-way constraints or other limitations. Suppliers and designers have expressed concern that lateral loads from the shafts may be transferred to the wall facing, causing excessive deformation. Procedures currently available to design MSE walls to resist internal lateral loads are very conservative isolating the shafts from the backfill or the using extremely large shafts to minimize deflection have been adopted. These designs are very expensive and in some cases lead to other problems. Results from this research project are expected to lead to much more cost effective designs on subsequent KDOT projects. We expect that the results will lead to improved national design standards for this type of construction as well.

Seven test shafts and 6 reaction shafts were constructed at the tests site, with some of the shafts socketed into the underlying limestone and shale bedrock. All of the test shafts were located within the reinforced backfill zone of the wall, varying the distance between the shaft and the wall face. Single shafts and shaft groups were loaded laterally. The wall face, reinforcing geogrid materials, and backfill were instrumented to measure loads, strains, and movements. The shafts were built with inclinometer casings to allow measurement of shaft deflections using an inclinometer during the tests. Many of the materials and construction work for the wall and shafts were made as in-kind donations by various companies, including Tensar who supplied the geogrid. KDOT Maintenance personnel perfomed most of the construction work and provided support for the load tests.

The tests took place between November 5th and 16th. I was on site the 12th through 16th to observe the tests, provide oversight, and assist Chris Kohlhof of AFT with running the tests. You can see a photo album or slideshow of some photos from my time at the site by clicking below.

 

KDOT Wall

Dr. Bob Parsons, P.E. of the University of Kansas Department of Civil, Environmental and Architectual Engineering will concentrate on analyzing the data concenring the wall and the backfill. DBA will analyze the lateral load tests data to derive p-y relationships for shaft design and will prepare a report on the load tests that includes design recommendations.

 

Technorati : , , , , , , , ,

Updated – GEC No. 8: Design and Construction of Continuous Flight Auger Piles – It’s Finally Here!

11/30-07 Update! – GEC No. 8 is now up on the FHWA web site. You can download it here.

Yes, folks, GEC 8 is finally complete! The publication version of Geotechnical Engineering Circular No.8: Design and Construction of Continuous Flight Auger Piles will soon be available from the FHWA Geotechnical Web Site. If you want an official sneak peek at GEC 8, just click here to get the PDF (approx. 10 MB). This circular is part of FHWA’s efforts to implement the use of CFA piles as a viable foundation alternative for transportation structures. We’ll post a notice when GEC 8 is on the FHWA web site.