The Wisconsin DOT was set to request bids this week for repairs to the Leo Frigo Memorial Bridge on I-43 in Green Bay, with an anticipated start of construction on November 4th and reopening of the bridge on January 17th.  The repair will consist of using drilled shafts installed adjacent to the existing piers with a post-tensioned extension of the pile cap to transfer the loads to the shafts.  A schematic of the design from Wisconsin DOT (via Milwaukee Wisconsin Journal Sentinel)

Scot Becker, director of the Bureau of Structures and the state’s bridge engineer, said the fix will consist of installing four concrete shafts beneath five affected piers to take over support from corroded underground steel structures, called pilings. Then, the bridge itself will be jacked up 2 feet, and concrete and steel will be poured to keep the bridge in position.

The bridge, which spans the Fox River in Green Bay, has been closed since late September, after pilings became corroded and buckled under one of the piers, causing a 400-foot-long section of the bridge to sink 2 feet. Since then, it has drooped another half inch, and the state is monitoring the bridge for further movement.

An investigation concentrating mainly in the area from Quincy St. to the Fox River found that soil surrounding the pier contained industrial byproducts over wetlands, which caused the corrosion.

Temporary supports are already being installed by Lunda to shore up the sagging spans until the repairs can be completed.