Tag Archives: Foundation Engineering

US 231 Emergency Slide Repair – Laceys Spring, Alabama

DBA has the great fortune to be working with the Alabama Department of Transportation (ALDOT) on a very interesting bridge project in Lacey’s Spring, Alabama just south of Huntsville, Alabama.  On February 12 and 13, 2020 a large landslide occurred on SR-53 (US-231) at milepost 301.7 in Morgan County approximately 1.7 miles south of the Laceys Spring Community.  The slide completely severed the 4-lane divided highway which is a major commuting route between Huntsville and several communities south of the city.  Many of the workers at the U.S. Army Redstone Arsenal, NASA Marshall Space Flight Center, and the contractors and vendors that support these two major installations live in the communities impacted by the closure of the highway.  Detours were established on existing state and county roads, but these added 30 to 60 minutes to commute times, depending on time of day.  ALDOT was under significant pressure from the impacted communities to quickly solve the problem and reopen the road.

ALDOT drill rigs performing exploratory drilling (DBA)

 

ALDOT drilling crews were immediately mobilized to the site to begin drilling exploratory borings and install slope inclinometer casings for monitoring slide movements.  The Department of Civil Engineering at Auburn University was engaged to perform geophysical testing in conjunction with an existing research project for ALDOT.  Geotechnical engineering firm TTL also assisted with field investigation efforts. 

DBA and ALDOT immediately began evaluating several alternate concepts for stabilizing the slide and reopening the road during the soil and rock exploratory drilling.  The design team looked at several retaining wall options, a complete rebuild of the roadway, and bridges.  ALDOT selected a solution that removed most of the existing roadway embankments (built in 1947 and 1970) to reduce loading on the slope and then spanning the slide area with bridges built on the existing road alignments, with the bridges designed to withstand future movements of the slope.  Excavation was begun by Reed Contracting before bridge design was complete in order for the rough grading to be done before the bridge contractor mobilized.

The bridges are two-lane structures, one Northbound and one Southbound, each about 947 ft in length.  The superstructure is AASHTO BT-72 concrete girders and a concrete deck.  There are seven spans in each bridge each about 135ft long.  The grading work was begun while the bridge was still being designed to accelerate the schedule and shorten the time the road would be closed.

The foundations for each pier are a pair of 9.5ft diameter, permanently cased drilled shafts with 9ft diameter rock sockets.  The sockets are 14ft long into the limestone and shale bedrock.  The limestone uniaxial compressive strengths range from 10,820 psi to 28,100 psi. 

After much design and analysis in a highly compressed schedule, a bridge contract was let for bid in early May 2020, less than 3 months after the slide occurred.  Brasfield & Gorrie was the successful bidder and awarded a $15 million contract that has incentives for finishing early, and disincentives for finishing late. 

 

ALDOT UAV flight June 16, 2020

ALDOT UAV flight July 07, 2020

ALDOT UAV flight July 23, 2020

ALDOT UAV flight July 28, 2020

ALDOT UAV Flight Aug 08, 2020

ALDOT UAV Flight Sep 2, 2020

ALDOT UAV Flight Sep 15, 2020

 

Excavating first shaft on the site (DBA)

 

A.H. Beck (Beck) is the drilled shaft contractor, drilling each shaft, placing reinforcement, and placing concrete.   The 9.5ft diameter permanent casing is 5/8 inch wall thickness spiral weld 60ksi steel fabricated by Nucor in Birmingham, Alabama.  The shafts are reinforced with a 1.5inch wall thickness, 8ft diameter, 60ksi steel pipe. These pipes were rolled and welded by Favor Steel in Birmingham, Alabama before being trucked to the site.  The steel plate was manufactured by SSAB in Axis, Alabama near Mobile.  So, the structural steel pipes were completely Alabama-made and the steel travel almost the length of the state!

8ft diameter x 1.5in wall steel pipe for shaft reinforcement (DBA)

 

Inner structural pipe (1.5in) and outer casing (5/8in) (DBA)

 

The pair of shafts for each pier is connected by a reinforced concrete grade beam 10ft wide by 7ft high by 46ft long. To connect the shafts to the grade beam, a 14ft long reinforcement cage is placed in each shaft, embedded 8ft into the shaft with 6ft embedded in the grade beam. The cage consists of 28 No.18 Grade 75 bars.

Grade beam at NB Bent 7 with column steel (DBA)

 

Completed shaft with reinforcing cage to embed in grade beam (DBA)

 

The project includes a robust instrumentation plan with ShapeArray inclinometers installed in each shaft and in the slope, supplemented by traditional inclinometers in the slope and vibrating piezometers to monitor groundwater levels.  DBA and ALDOT will monitor the bridge and slope, intending to be able to measure displacement and calculate strain and loads in the shafts should the slope move again in the future.

Foundations are scheduled to be completed by the end of July 2020.  The deadline to have the bridge open to traffic is early December, 2020, but Brasfield and Gorrie has an aggressive plan to complete the project early and earn the bonus for early completion.   Volkert is the CE&I Consultant on the project for ALDOT, providing construction management and inspection services for the project.

Click HERE for some of the photos DBA team members have taken during construction.

To see aerial views from ALDOT’s UAV flight taken on July 10, 2020, click HERE.

 

 

DBA is growing again – welcome to Ali, Ben, and Mark!

Well, we are at it again.  The first 5 months of 2016 have seen us add three new faces of the new website creator.  So now, drum roll, please………

Ali Leib, E.I.

Ali 2016-1

Ali was a summer intern at DBA in 2014 and 2015 and joined us full time as a staff engineer in February.  She is a recent graduate of the University of Tennessee (Go Vols!) where she completed both her B.S. and M.S. in civil engineering. While completing her M.S., she was a teaching assistant in charge of grading lab reports for the structural and geotechnical undergraduate labs. She was also a research assistant under Dr. Dayakar Penumadu, resulting in her thesis: “Effect of Particle Morphology on the Deformation Behavior of Sand under Monotonic Loading Conditions.”  Unlike most of the rest of us, Ali insists that she will not be conforming to the (mostly) standard DBA hair style.  Ali will work in our Knoxville, Tennessee office.

Mark Madgett, P.E.

Mark Madgett_s

 

Mark received a BS and MS degree in Civil Engineering at the University of Tennessee, while working on research for TDOT to improve pavement design methods.  He has worked in both consulting and construction for the last 22 years, focusing primarily on deep foundations in the Southeastern US.  As a consultant, Mark gained extensive field experience with deep foundation construction techniques and the impacts on design.  In 2006, he began working for Seaboard Foundations, opening a green field office in Tri-Cities TN as the district manager.  In his role as design engineer for Seaboard Foundations, Mark has implemented design-build techniques in many markets (energy, institutional, commercial, transportation, and healthcare you can supplement if you find Kratom online and other natural products) that vastly improved the constructability and reduced the costs of deep foundation systems for his clients.  Mark will also work outr of our Knoxville, Tennessee office.

Ben Turner, Ph. D., P.E.

Ben recently completed his Ph.D. in geotechnical earthquake engineering at UCLA with an emphasis on the transfer of forces between the ground and foundation elements during seismic loading. Prior to starting at UCLA, he worked for two years for the Los Angeles office of Shannon & Wilson, Inc.  Ben worked in both construction and geotechnical firms while attending school for his B.S. and M.S. degrees. His experience includes: design, construction, and load testing of deep foundations;  geotechnical earthquake engineering including soil-structure interaction, seismic hazard analysis, site response, liquefaction triggering analysis and mitigation of liquefaction-induced ground failure; and, characterization of structural behavior of reinforced concrete foundations.  Here are two of the publications resulting from his dissertation work:

Turner, B., Brandenberg, S., and Stewart, J. (). “Case Study of Parallel Bridges Affected by Liquefaction and Lateral Spreading.” J. Geotech. Geoenviron. Eng. , 10.1061/(ASCE)GT.1943-5606.0001480 , 05016001.

Turner, B. and Brandenberg, S. (2015) “Pile Pinning and Interaction of Adjacent Foundations During Lateral Spreading”, DFI Journal, Volume 9, Issue 2.

Ben will anchor the West Coast Region of DBA, working from San Luis Obispo , California.

 

Incredible Pictures of St Croix Crossing Construction

St Croix Crossing Superstructure Construction
St Croix Crossing Superstructure Construction (photo courtesy of MnDOT)

Precast Box Segments
Precast Box Segments (photo courtesy of MnDOT)

Although foundation work has been complete at the St Croix Crossing project for quite some time now, MnDOT has recently posted some really amazing photos of the superstructure construction, or dome shelter of this huge bridge  on the project site and Facebook page.

The St Croix Crossing Bridge is an extradosed bridge, which is something of a cross between a segmental box girder and cable-stayed bridge.  The scale of the massive concrete segments can be seen in the picture above in comparison to the barge the segments are sitting on and some of the equipment in the background.

Goethals Bridge – Up and out of the ground

(Post and photos provided by John Turner, Ph.D., P.E., D.GE of DBA.)

DBA has had the privilege to be the geotechnical/foundation engineer for the Goethals Bridge Replacement (GBR)Project, a design-build project for the Port Authority of New York & New Jersey (PANYNJ). The project will replace the existing Goethals Bridge that was built in the 1920s and carries I-278 over the Arthur Kill River between Elizabeth, New Jersey and Staten Island, New York.

Construction of drilled shafts continues as the superstructure begins to emerge over the skyline between Elizabeth, NJ and Staten Island, NY.  The new bridge will be a dual-span 1,983-ft long cable-stayed bridge with approach spans of over 2,500 ft on each side.  The bridge is supported on over 200 drilled shaft foundations ranging in diameter from 4.5 ft to 10 ft and socketed into Passaic Formation siltstone.

Goethals April 2016

The GBR is a Public-Private Partnership (P3) that represents a major milestone for the PANYNJ in its distinguished history of bridge building in the greater New York City metropolitan area.  The existing Goethals Bridge along with the Outerbridge Crossing and the Bayonne Bridge comprise the three Port Authority bridges connecting Staten Island with New Jersey.  The Goethals Bridge and the Outerbridge Crossing are cantilever truss structures and both opened on the same day in 1928. They were designed by J.A.L. Waddell under the supervision of the eminent engineer Othmar H. Ammann (1879-1965), who was the designer of many other iconic bridges in the NY City area including the Bayonne Bridge (1931), the George Washington Bridge (1931), and the Verrazano Narrows Bridge (1964).  The designer of record for the replacement Goethals Bridge is Parsons Corporation, which is the successor firm of Robinson & Steinman, whose principal David B. Steinman was also a notable NY area bridge designer and a contemporary and rival of O.H. Ammann.

Each main pylon tower of the GBR is supported on a group of six 9-ft diameter drilled shafts and each anchor pier is supported by two 10-ft diameter shafts.  Approach piers are two-column bents with each column supported on a rock-socketed drilled shaft.

Goethals shaft 1

DBA is the foundation design engineer of record and this project provides an example of how rock-socketed drilled shafts can provide a reliable and cost-effective means of supporting a major bridge by taking advantage of the high resistances that can be achieved.  Key factors involved in taking advantage of rock sockets for this project were:  (1) load testing to demonstrate high axial resistances (>30 ksf side resistance and  >300 ksf base resistance), (2) utilization of all relevant construction QC/QA tools to ensure that rock sockets are constructed in a manner that is consistent with construction of the load-tested shafts that provide the basis of the design, (3) close collaboration between all members of the design-build team, and (4) adequate subsurface characterization, especially a thorough characterization of rock characteristics and their effect on socket resistances. Load testing for this project demonstrates that side and base resistances can be used in combination to design rock socketed shafts for axial loading.  This approach avoids the use of unnecessarily deep sockets, thereby minimizing the associated construction risks and costs.

Goethals rendering

The GBR project developer is NYNJ Link Developer, LLC and construction is being performed by a joint venture of Kiewit-Weeks-Massman (KWM).  Parsons is the lead designer.  A construction web-cam and additional information on the GBR can be found at the Port Authority’s website: http://www.panynj.gov/bridges-tunnels/goethals-bridge-replacement.html

Foundations for the New Sacremento Entertainment and Sports Center

 

kingsarenanew_670

Contributed by Rob Saunders, P.E. – DBA

DBA has been working on an exciting new project currently under construction in downtown Sacramento, California: the new Sacramento Arena, known as the Entertainment and Sports Center (ESC).  The ESC will be a multi-use, publicly owned indoor arena. The Sacramento Kings will be the primary tenant and the arena is expected to host other indoor sports and music concerts, as well.  Once completed, the ESC will replace Sleep Train Arena as the home of the Kings.  According to Kings Chairman Vivek Ranadive, the 17,500-seat arena will be “one of the most iconic structures on the planet … It’s going to put Sacramento on the world map.”

turner

Turner Construction is the head of development for the new arena. Malcolm Drilling Company was awarded the contract to design and construct the foundation system.  DBA worked closely with Malcolm to design Omega piles (a drilled and grouted displacement pile) to serve as the foundations for the new arena.  The site presented unique design challenges, including liquefiable soil conditions and existing deep foundations from the demolisLogo_Malcolm_Stacked_Bluehed portion of the Downtown Plaza.

DBA’s design incorporates 18” and 24”  Omega piles.  An extensive site-specific load test program was performed to determine the axial resistances of the piles.  Eight test piles were instrumented with strain gauges to measure the load distribution in the piles.  Supplemental cone penetration testing was performed following load testing to better correlate the load test results with the subsurface conditions.

The piles were designed to resist ground motions from seismic events using site-specific ground curvature data developed by Pacific Engineering and Analysis. The piles were designed to resist the curvature at the anticipated pile section with only a single center reinforcing bar, eliminating the need to extend the entire cage to the bottom of the pile. This detail in the design is very important to ease the pile installation for the site conditions.

The final design incorporates a total of 952 piles to support the arena structure (346 18” dia. Piles and 606 24” dia. piles). The new arena is estimated to cost $477 million, with $255 million of that being funded by the City of Sacramento. The rest of the arena ($222 million) will be funded by the Sacramento Kings. Construction began October 29, 2014 and is planned to be completed by October of 2016.

The groundbreaking for the project was featured by the Sacremento Bee on October 29, 2014 (link).

Kansas City Load Test Photos Added

BPU Load Test

Last spring, DBA conducted a construction phase load test program for a U.S. Army Corps of Engineers floodwall improvement project  along the Missouri River in Kansas City, Kansas.  Located on property owned and maintained by the Kansas City Board of Public Utilities (BPU), the BPU floodwall was slated for structural improvements including a series of buttresses founded on 24-in drilled shafts.  As part of the project contract a load test program performed under the direction of a qualified P.E. and D.GE was required.  General contractor L.G. Barcus & Sons, Inc., secured our Paul Axtell, P.E., D.GE as the qualified load test expert.  DBA teamed up with load testing subcontractor Applied Foundation Testing, Inc., to perform the static load tests.

The load test program requirements included three test shafts, a statically loaded axial test shaft, a statically loaded lateral test shaft, and a combined statically loaded axial and lateral test shaft.  The required combined lateral and axial test shaft provided some unique challenges with respect to applying the loads and collecting data.  As can be seen in the picture above, the axial load was applied using dead weights.

We have added selected pictures from this unique project to our web albums, which can be viewed here.

New PEER Report – Evaluation of Collapse and Non-Collapse of Parallel Bridges Affected by Liquefaction and Lateral Spreading

webPEER-2014-10-Brandenberg

Our own Ben Turner (future Dr. Turner!) was lead author on a report by the Pacific Earthquake Engineering Research Center (PEER) on liquefaction and lateral spreading effects on bridges. The report is titled “Evaluation of Collapse and Non-Collapse of Parallel Bridges Affected by Liquefaction and Lateral Spreading”. Ben’s coauthors are Dr. Scott J. Brandenberg and Dr. Jonathan P. Stewart of the Department of Civil and Environmental Engineering at UCLA. From the abstract:

The Pacific Earthquake Engineering Research Center and the California Department of Transportation have recently developed design guidelines for computing foundation demands during lateral spreading using equivalent static analysis (ESA) procedures. In this study, ESA procedures are applied to two parallel bridges that were damaged during the 2010 M 7.2 El Mayor-Cucapah earthquake in Baja California, Mexico. The bridges are both located approximately 15 km from the surface rupture of the fault on soft alluvial soil site conditions. Estimated median ground motions in the area in the absence of liquefaction triggering are peak ground  accelerations = 0.27g and peak ground velocity = 38 cm/sec (RotD50 components). The bridges are structurally similar and both are supported on deep foundations, yet they performed differently during the earthquake. A span of the pile-supported railroad bridge collapsed, whereas the drilled-shaft-supported highway bridge suffered only moderate damage and remained in service following the earthquake. The ESA procedures applied to the structures using a consistent and repeatable framework for developing input parameters captured both the collapse of the railroad bridge and the performance of the highway bridge. Discussion is provided on selection of the geotechnical and structural modeling parameters as well as combining inertial demands with kinematic demands from lateral spreading.

This report is part of Ben’s work on his doctoral dissertation. You can download the report by clicking on the linked citation below.

Turner, B., Brandenberg, S.J. and Stewart, J.P. (2014). “Evaluation of Collapse and Non-Collapse of Parallel Bridges Affected by Liquefaction and Lateral Spreading”, PEER Report 2014/10, Pacific Earthquake Engineering Research Center, University of California, Berkley, August, 2014, 94pp.

Goethals Bridge Replacement – Webcam!

goethals-replacement-logo

DBA is on the design-build team that is replacing the Goethals Bridge for the Port Authority of New York and New Jersey (PANYNJ). We are not able to post much about the project or our involvement due to security agreements. However, the PANYNJ has a public website for the project (http://www.panynj.gov/bridges-tunnels/goethals-bridge-replacement.html) that has several webcams.  As is the case with most big projects these days, the webcams are a common feature and show some great views of the project.

To give you an idea of what the project involves, here is a summary from the PANYNJ site:

The replacement bridge will be located directly south of the existing bridge and will provide:

  • Three 12-foot-wide lanes in each direction replacing the current two narrow 10-foot-wide lanes
  • A 12-foot-wide outer shoulder and a 5-foot-wide inner shoulder in each direction
  • A 10-foot-wide sidewalk/bikeway along the northern edge of the New Jersey-bound roadway
  • Improved safety conditions and performance reliability by meeting current geometric design, structural integrity, security and seismic standards, and reduces life-cycle cost
  • A central corridor between the eastbound and westbound roadway decks, sufficient to accommodate potential transit service
  • State-of-the-art smart bridge technology

The project also includes the demolition of the existing bridge upon completion of the replacement bridge.

You can learn more about the project at the same web site.  There is also a site for the current bridge, including history of the construction, etc.

Raising the Leo Frigo Bridge

Work to begin lifting the sagging portions of the Leo Frigo Memorial Bridge on I-43 in Green Bay, Wisconsin is scheduled to begin Tuesday.  According to the Green Bay Press Gazette,  Zenith Tech Inc. is working on the repairs.  It will be a BIG lift, indeed…..

Raising the troubled Leo Frigo Memorial Bridge back into place will be a task equivalent to hoisting an entire fleet of 747s into the air.

Experts have calculated that the sagging section of Green Bay’s distressed bridge weighs more than 3 million pounds, or about 1,600 tons.

……

Zenith Tech crews are expected to spend several days using hydraulic jacks to boost the Leo Frigo back into position — a process that will go slow, by design.

……

Starting with the northbound lanes, Zenith Tech will insert 10 hydraulic jacks beneath the bridge deck and operate them all simultaneously to raise the platform. Each jack will be exerting enough pressure to support 183,000 pounds, although Dreher said their capacity is 50 percent greater than that — just in case it is needed.

Dreher said the jacks will be calibrated carefully to operate in perfect unison, so there is no risk of the bridge deck leaning one way or the other as it is elevated.

“You can’t just go in there and start jacking away,” he said. “It definitely takes some coordination and good communication.

A very challenging and interesting repair project.  Kudos to the Wisconsin DOT and all involved in getting the repairs done quickly.

See our previous posts here.

Drilled Shafts Complete at St Croix

Pier 9 FootingAs reported by the Minneapolis Star Tribune, Case Foundation recently finished constructing 40 drilled shafts at the St Croix River Crossing Project.  Since early June, Case has been working at a feverish pace to construct the drilled shaft foundations for the new extradosed bridge between Minnesota and Wisconsin.  As of November 8th, all of the drilled shafts are officially complete.  General contractor Kramer is working to finish the pier footings and support tower bases by early 2014.  Soon, the joint venture of Lunda and Ames will begin construction of the $380 million bridge superstructure.

As MnDOT’s foundation consultant for the project, DBA has been on site during much of the foundation construction over the past five months.  Some pictures taken during this time, along with several pictures from MnDOT are available for viewing on our Picasa Page.  More pictures and information can be found on the project website and Facebook Page, and the project can be viewed live via webcam.  Previous DBA blog posts about the main project and the predesign load test program can be found here.

DBA is pleased to wrap up its role on the St Croix Crossing Project with a very positive outlook.  The drilled shaft construction proceeded on schedule and as planned without unexpected challenges, and our strong client relationships with MnDOT continued to grow stronger.  It was also nice to see familar faces from Case, Braun Intertec, and Parsons Transportation Group, many of whom we worked with us at Hastings.  We very much look forward to working with these partners again in the future!