All posts by David Graham

PROJECT HIGHLIGHT: 30 CROSSING DESIGN-BUILD

DBA is pleased to be part of the Kiewit Massman Construction (KMC) design-build team delivering the first transportation design-build project in the State of Arkansas, 30 Crossing. The project will improve traffic patterns and capacity along a 3-mile urban corridor of Interstate 30 from the Interstate 630 interchange south of downtown Little Rock to the Interstate 40 interchange in North Little Rock. The project includes replacing the existing bridge over the Arkansas River with two bridges supporting 12 lanes of traffic. 30 Crossing is the capstone project of the Connecting Arkansas Program (CAP), one of the largest highway improvement programs ever undertaken by the Arkansas Department of Transportation (ArDOT).

Teamed with designers Burns & McDonnell and HDR, DBA is the lead geotechnical and foundation designer for the navigation unit and north approach unit of the new river bridges. The bridge foundations are 10-ft diameter drilled shafts socketed into shale bedrock. Due to the project’s proximity to the New Madrid Seismic zone, design of the bridges included seismic considerations for critical operational class structures. Geotechnical seismic analysis included liquefaction triggering and lateral spreading evaluation. DBA worked closely with the structural designers to consider kinematic loads induced by lateral spreading and the interaction of substructure and superstructure components during lateral spreading events. The north abutment includes a column supported MSE wall embankment (CSE). The CSE ground improvement is included to mitigate performance and stability issues associated with shallow, soft alluvial silts and liquefaction hazards associated with deeper, alluvial sands.

KMC is self-performing the drilled shaft construction and CSE installation. To date, all of the eastbound bridge drilled shafts have been installed in the river and for the north approach. The ground improvement elements as part of the CSE beneath the eastbound embankment has also been completed. Once the eastbound bridge is ready for traffic in 2022, both directions of Interstate 30 will be temporarily shifted to the eastbound bridge, and the existing bridge will be demolished to allow for construction of the westbound bridge in its place.

Senior Engineer, David Graham, P.E., is the geotechnical engineer of record and has been involved in all aspects of the project form pursuit phase to current construction activities with significant contribution and guidance of Senior Principal Engineer and COO, Paul Axtell, P.E., D.GE. Senior Engineer, Ben Turner, Ph.D., P.E., G.E., lead the geotechnical seismic design and analysis effort. Project Engineers, Dan Ding, Ph.D., P.E. and Nathan Glinski, P.E., continue to be heavily involved in construction support and observation.

Eastbound Pier 13
Westbound Pier 13 drilled shafts
Looking north from Pier 13 at Eastbound Piers 14 and 15

Photos Credit: DBA

Two Major Bridges in Minnesota Open to Traffic

St. Crox Crossing Extradosed Bridge; photo courtesy of MnDOT

Two DBA bridge projects in Minnesota opened to traffic recently.  The St. Croix Crossing near Stillwater and the Highway 53 Relocation in Virginia.  Both projects are milestones for MnDOT.  The St. Croix Crossing is the first extradosed bridge in the Midwest and only the second extradosed bridge in the United States.  The new Highway 53 Bridge is the tallest bridge in Minnesota.

Following a ribbon cutting and dedication ceremony on the morning of Wednesday, August 2nd, the St. Croix Crossing saw its first traffic later that evening and has already alleviated traffic congestion  in downtown Stillwater,  as intended.  The interstate project was also heralded as a noteworthy example of government cooperation by The Wall Street Journal.

After officially breaking ground just shy of two years ago,  the new Highway 53 bridge opened to traffic on September 15th.  A dedication ceremony was held underneath the bridge that morning with Minnesota Lt. Gov. Tina Smith and Congressman Rick Nolan in attendance.  In  anticipation of the new bridge, the iron range quad cities of Virginia, Eveleth, Gilbert, and Mountain Iron held a four-day, multi-event festive, Bridge Daze, in August.

Hwy 53 Bridge Across The Rouchleau Pit; photo courtesy of OxBlue construction cameras

TH 53 Bridge Begins to Rise from the Ground

Bridge and Subsurface Rendering
Bridge and Subsurface Rendering (rendering courtesy of MnDOT)

A lot has changed from a year ago at the TH 53 Bridge sight near Virginia, Minnesota.  This time last year, the design-phase test pile program was wrapping up with three Statnamic load tests and we had just completed our initial geologic field investigation.  Since then, significant excavation, rockfall protection, and foundation work has been completed.  During summer and fall of 2015, DBA worked closely with contractors Hoover Construction and Pacific Blasting to maintain rockfall protection throughout the East Abutment and Pier 1 (East Pier) excavation process.  Official ground breaking occurred last November and foundation work started shortly after.  A total of 32, 30-in micropile foundations have been installed by Veit Specialty Contracting  and Kiewet Infrastructure  has completed a temporary causeway across the massive Rouchleau Pit by placing over 300,000 cubic yards of fill.

With the foundations of both piers complete, and the pier towers are starting to rise up, where they will carry the bridge deck 200 ft above.  The abutments are also taking shape with rock bearing concrete footings now poured on both sides of the pit.  The only foundation work left is to install tieback anchors at the East Abutment, which will reduce the lateral loading of the tall piers. This bridge is going to get packed with cars once it´s completed, that means there´s going to be lots of accidents. It´s not a bad idea to call One Sure Insurance to get covered before all that.

In a little over a year, the bridge is scheduled to open to traffic.  You can keep track of the progress through the project web cam.

Current View of Site, Piers Beginning to Rise
Current View of Site, Piers Beginning to Rise (photo from OxBlue Web Cam)

Incredible Pictures of St Croix Crossing Construction

St Croix Crossing Superstructure Construction
St Croix Crossing Superstructure Construction (photo courtesy of MnDOT)
Precast Box Segments
Precast Box Segments (photo courtesy of MnDOT)

Although foundation work has been complete at the St Croix Crossing project for quite some time now, MnDOT has recently posted some really amazing photos of the superstructure construction, or dome shelter of this huge bridge  on the project site and Facebook page.

The St Croix Crossing Bridge is an extradosed bridge, which is something of a cross between a segmental box girder and cable-stayed bridge.  The scale of the massive concrete segments can be seen in the picture above in comparison to the barge the segments are sitting on and some of the equipment in the background.

Ground Breaking of New TH 53 Bridge in Minnesota

TH 53 Bridge

TH 53 Bridge, artistic rendering courtesy of MnDOT

The official groundbreaking for the Trunk Highway (TH) 53 Bridge and Relocation Project occurred last week at the project site in Virginia, Minnesota.  The bridge, which is the main element of the project, will span the Rouchleau Iron Ore Mine Pit.  The project is scheduled to be completed in a brisk two years in order to allow for mining where a section of TH 53 is currently located.  Upon completion the 1,100-foot long bridge will be Minnesota’s highest, with the roadway sitting approximately 330 feet above the bottom of the floor of the Rouchleau Pit.  Kiewit was selected as the general contractor for the project with Veit Specialty Contracting as the foundation contractor.

Foundation construction will start in late November or early December with the installation of 30-inch diameter micropile foundations for the western pier of the three span, steel plate girder bridge.  Although the foundation work is just about to get started, DBA has been hard at work on the project for over a year.  DBA first got involved as a consultant to MnDOT for the design-phase load test program conducted last fall.  Since then, DBA was contracted as the geotechnical engineer of record for the project.  Working with bridge designer Parsons, DBA designed the bridge foundations, an anchored abutment, and rockfall hazard mitigation systems for this geologically challenging site.  DBA has also analyzed several soil and rock slopes to verify stability of the bridge and roadway.

Most recently, some of us were on site to inspect some of the rockfall protection elements on the east side of the mine pit. Last week we spent two days climbing and repelling a on a portion of the eastern highwall, which is currently covered in rockfall protection drapery. The drapery was installed for the protection of workers excavating rock for the eastern bridge pier.   The drapery was installed by Pacific Blasting in association with Hoover Construction.  Some pictures from our drapery inspection visit are below.

For more information about the project, click here, and for our previous blog posts on this project, click here.

John and Paul provide some scale to this picture as they work their way down the drapery.

 John concentrating as he inspects the drapery seam as he decends.

DBA Engineers Perform “Extreme” Geologic Investigation

DBA engineers prepare to go over the edge of the 200-ft tall west wall of the Rouchleau mine pit with the load test site in the background. From left to right: David Graham, Nathan Glinski, Ryan Turner, and Paul Axtell
DBA engineers prepare to go over the edge of the 200-ft tall west wall of the Rouchleau mine pit with the load test site in the background. From left to right: David Graham, Nathan Glinski, and Paul Axtell (far right).

DBA is currently working with structural designer Parsons to design what will be Minnesota’s tallest bridge.  The bridge will span the currently inactive Rouchleau open pit iron ore mine near Virginia, Minnesota. MnDOT is moving the alignment of the existing Hwy 53 to make way for future mining in the area.  DBA is the lead geotechnical designer on the project in addition to being contracted as MnDOT’s load test expert for the ongoing design phase load test program.

As part of our site investigation to gather information on rock fall and the site geology, five DBA engineers (John Turner, Paul Axtell, Tim Siegel, Nathan Glinksi, and David Graham) got up close and personal with the site by rappelling off the near vertical cut faces on either side of the Rouchleau pit! Traversing the over 200-ft tall cut faces of the nearly 2-billion year Biwabik Formation rock formation by rope and harness, we collected valuable geologic data.  We also took some great pictures like the ones posted to our Google Photos account.  In addition to the still pictures, we took some videos of a few rock fall tests, which are on our YouTube channel.

If you would like to know more about this interesting project on Minnesota’s Iron Range, you can check out our project summary sheet, visit MnDOT’s project page, or stay tuned to this blog for more updates.  There is also an online article about the project that was recently published by Civil Engineering Magazine.

Kansas City Load Test Photos Added

BPU Load Test

Last spring, DBA conducted a construction phase load test program for a U.S. Army Corps of Engineers floodwall improvement project  along the Missouri River in Kansas City, Kansas.  Located on property owned and maintained by the Kansas City Board of Public Utilities (BPU), the BPU floodwall was slated for structural improvements including a series of buttresses founded on 24-in drilled shafts.  As part of the project contract a load test program performed under the direction of a qualified P.E. and D.GE was required.  General contractor L.G. Barcus & Sons, Inc., secured our Paul Axtell, P.E., D.GE as the qualified load test expert.  DBA teamed up with load testing subcontractor Applied Foundation Testing, Inc., to perform the static load tests.

The load test program requirements included three test shafts, a statically loaded axial test shaft, a statically loaded lateral test shaft, and a combined statically loaded axial and lateral test shaft.  The required combined lateral and axial test shaft provided some unique challenges with respect to applying the loads and collecting data.  As can be seen in the picture above, the axial load was applied using dead weights.

We have added selected pictures from this unique project to our web albums, which can be viewed here.

Tim Siegel Appointed New Co-Editor of DFI Journal

As Robert recently posted, Dan is taking on new roles at the Deep Foundations Institute (DFI) as a member of the DFI Educational Trust Board and as treasurer of the DFI Board of Trustees.  Tim Siegel is now stepping in to fill Dan’s former role as co-editor of the DFI Journal.  From DFI:

February 24, 2014, Hawthorne NJ: Maney Publishing and the Deep Foundations Institute (DFI) are pleased to announce the appointment of Anne Lemnitzer and Timothy C. Siegel as the new co-editors of DFI Journal: The Journal of the Deep Foundations Institute. They will succeed lead editors Ali Porbaha and Dan Brown, who are stepping down after being editors since the Journal’s inception, and Zia Zafir, who will remain on the editorial board.

Timothy Siegel is a principal engineer with Dan Brown and Associates PC and member of the adjunct faculty at the University of Tennessee. He holds a B.S. and M.S. in Civil Engineering from Georgia Institute of Technology and has spent over 20 years working in industry. He is a member of the DFI’s Ground Improvement and Seismic and Lateral Loads Committees and has authored or co-authored over 45 technical papers and has presented at conferences throughout the USA.

Anne Lemnitzer is assistant professor at the University of California in Irvine. She holds a Ph.D. in structural engineering from UCLA as well as an M.S. in Geotechnical Engineering from California State University, Long Beach and B.S. from the University of Applied Science in Leipzig, Germany, where she was awarded a Fulbright Scholarship to continue her education. Her research interests lie at the interface of geotechnical and structural earthquake engineering.

Tim Siegel comments, “At no time in history has the practice of foundation engineering been as challenging as it is now. Ambitious projects, stringent design codes, the likelihood of litigation, and high expectations require engineers to effectively intertwine theory and experience. At a time when many technical journals are focused on the former, the DFI Journal plays a vital role by offering a balance between theory and experience. This is one reason that DFI Journal is a leading platform for technology transfer on design and construction of deep foundations and ground improvement.”

Anne Lemnitzer comments, “I am excited to work with my colleague Tim Siegel in serving as co-editor of the DFI Journal and hope to further enhance its reputation and circulation in the geotechnical community. We are determined to seek the best deep foundation research from across the world and combine it with the most innovative design projects currently built, hereby creating a unique stage for intellectual exchange, transfer of knowledge and professional development. The DFI Journal provides this alternative approach compared to traditional scientific journals and we are looking forward to widening the audience through hands-on, understandable publications that can make lasting impacts on our foundation industry.”

“DFI is excited to have members, Tim Siegel and Anne Lemnitzer taking the lead as Journal co-editors as we strive to increase the readership and frequency of the publication. The Journal is the perfect vehicle for achieving DFI’s mission to disseminate practical and useful content to the deep foundations construction industry and be the information resource for design and construction of foundations and excavations. We are confident the new editors will provide excellent insight, technical expertise and leadership in their new role,” says Theresa Rappaport, DFI executive director.

Tim, congratulations and thank you for your contributions to the industry!

Replacing the 89 Year Old Sellwood Bridge

DBA has had the pleasure of working with T.Y. Lin and SlaydenSundt JV in their effort to replace the Sellwood Bridge over the Willamette River in Multnomah County, Oregon, near Portland. Designed by Gustav Lindenthal, the existing Sellwood Bridge was constructed in 1925 to replace the Spokane Street Ferry, connecting the communities of Sellwood and West Portland.  In response to budget issues at the time, the Sellwood Bridge design was scaled back to minimize costs. Fast forward to 2014 and the existing Sellwood Bridge is now the only four-span continuous truss highway bridge in Oregon and possibly the nation. The bridge is extremely narrow, two lanes, no shoulder or median, and one small 4-ft sidewalk.  In addition to these shortcomings in design with respect to the modern age, the west end of the bridge was constructed on fill, and the hillside above the bridge is now slowly sliding toward the river. Ground movements have caused some of the girders to crack. Furthermore, the existing bridge was not designed to any seismic standards which present a major concern given the bridge’s location in the seismically active Pacific Northwest.

The new Sellwood Bridge will be a deck arch structure with three arches supporting the deck of the main river spans and is designed to the latest seismic standards. It will feature two 12-ft travel lanes, two-12 ft shared use sidewalks, and two 6.5-ft bike lane/emergency shoulders. Multnomah County is using the existing bridge truss on temporary pile foundations as a detour to save time and money during construction with minimal impact to traffic, people can always get quick loans without credit check process at any time if they have financial problems. According to www.cyclonebuildings.com, the original bridge truss was shifted on January 19, 2013. Complicating the move was the enormity of the bridge, an 1100-ft single truss weighing 3400 tons. In addition to the size and weight of the span, old age and its curved alignment added to the technical challenges. The impressive move took only 14 hours.  The detour bridge is currently fully operational and will continue to carry traffic until the summer of 2015 when the new bridge is scheduled to open.

DBA played key roles in the design and construction of the main arch piers. As part of the VE Design, DBA assumed engineering responsibility for the 10-ft diameter drilled shafts supporting Piers 4, 5, and 6 (4 & 5 being in the river and 6 on the eastern shore).  The lengths of these shafts ranged from 81 ft to 225 ft through a number of subsurface conditions which posed many challenges to construction. Subsurface conditions ranged from large loose cobbles/gravel (Catastrophic Flood Deposits) to cemented cobbles and gravel (Troutdale Formation), to very hard intact basalt bedrock. Due to the challenging geologic conditions and variability of these conditions across the site, DBA implemented an observational method in which the final shaft length determination was made on the basis of our on-site observations in relation to a set of predefined criteria. This approach provided the necessary flexibility to efficiently confront different subsurface conditions in a timely manner. Drilling subcontractor Malcolm Drilling successfully completed construction of the last of these shafts in mid-October 2013.

You can learn more about the bridge and the project at Multnomah County’s website, SellwoodBridge.org. The website has current field work updates, photo gallery, history of the project, and a live construction camera with daily, weekly, and monthly time-lapse videos.  There is also a time-lapse of the moving of the old truss.

written by Nathan Glinski, edited by David Graham

Robert Receives NHI Award and Paul Becomes DFI Committee Chair

WRT_NHI

It was recently announced that Robert Thompson is being recognized by the National Highway Institute (NHI) as an NHI Instructor of Excellence for fiscal year 2012.  This award is given to NHI instructors who receive consistently high classroom evaluation scores, demonstrated commitment to the NHI adult learning philosophy, and for maintaining the highest standard of quality for transportation training.  Here are the congratulatory words of NHI Director of Training Programs, Richard Barnaby:

Your nomination and selection for this award shows that training participants value the instruction you provide, that you stand far ahead of your peers, and that you have captured the respect of HHI’s Training Program Managers.  This year you have continuously provided high quality instruction, shared your vast expertise and real world experiences, and have exceeded performance expectations.

Robert currently serves as an instructor for two NHI courses, NHI Course 132069, Driven Pile Foundation Inspection with co-instructor Keith Bennett of Gannett-Flemming and NHI Course 132014, Drilled Shafts – Construction Procedures and LRFD Design Methods with co-instructors Dan Brown and John Turner of DBA.

That is most certainly a job well done, Robert!

Paul Axtell

We would also like to announce that Paul Axtell has been named as the new chair of the Deep Foundations Institute (DFI) Drilled Shaft Committee, following Tom Hart of Black & Veatch.  Paul certainly deserves the honor of this roll given his participation and contributions to the Drilled Shaft Committee.

Congratulations, Paul!