Get the New FHWA Drilled Shaft Manual

Get the NCHRP Synthesis 418 – Pile Criteria From Test Pile Data

Dan’s Speaking Schedule

September 12-13, 2012: Concrete used in Drilled Shaft Construction - ADSC/DFI Drilled Shaft Seminar - Denver, Colorado

October 26, 2012: Factors Affecting the Selection and Use of Drilled Shafts for Transportation Infrastructure Projects - 26th Central Pennsylvania Geotechnical Conference - ASCE/DFI - Hershey, Pennsylvania

Other DBA Team Speaking Appearances

John Turner (September 12-13, 2012): Analysis & Design of Drilled Shafts - ADSC/DFI Drilled Shaft Seminar - Denver, Colorado

John Turner (September 12-13, 2012): Techniques for Drilled Shaft Construction - ADSC/DFI Drilled Shaft Seminar - Denver, Colorado

Conferences, Meetings, Seminars, Workshops

Bridge updates – kcICON, Audubon, Beck Street

As geotechnical/foundation engineers, we don’t usually get to see much of what happens on a project after the foundations are completed, especially a project like a large bridge that can take years to complete.  Technology such as the Internet, webcams, and digital photography have made it easy for us to see how things are progressing on projects, as well as maybe get images of the completed structure.  As I have noted before, some projects are using Twitter and Facebook to keep the public informed on closures, delays or overall project progress as part of good public relations.  Her are some updates on a few of our recent projects.

 

kcICON:

The main span is well underway, including the cables.  The kcICON Facebook page is here.

PASEOBSOimage10-05-17_16-20-11-00 PASEOBWEimage10-05-04_07-40-00-43

 

Audubon Bridge:

Check out the webcam.  You can download images if you like.  YOu can also do a time-lapse from Day 1 of construction.

image image

 

Beck Street Bridge:

Part of the I-15 Express Link project in Salt Lake City, UT.   The photos below I obtained from the photos page on the project web site.  We were involved in the design and construction of the foundations for the Beck Street Bridge only.

5-5-10-03  picture-123-scopy_0_picture-158-s

Geo-Florida 2010 Papers posted

geoflorida2010 logo

 

Audubon graph-GeoFlorida-Dapp

 

Papers by Dan, Steve, and Tim that were included in the GeoFlorida 2010 conference have been uploaded to our Publications page.  Dan and Steve co-authored a paper on the test program of the base grouted drilled shafts for the Audubon Bridge.  Tim co-authored a paper with Willie NeSmith of Berkel and Company Contractors, Inc. on plate load testing of displacement grout columns.  Dan was also a co-author with several others on a paper on jet grouting for improved pile lateral capacity.

 

Dapp, S.D. and Brown, D.A. (2010). “Evaluation of Base Grouted Drilled Shafts at the Audubon Bridge”, GeoFlorida 2010, Advances in Analysis, Modeling and Design, Geotechnical Special Publication No. 199, ASCE, pp1553-1562.

Rollins, K.M., Herbst, M., Adsero, M. and Brown, D.A. (2010) “Jet Grouting and Soil Mixing for Increased Lateral Pile Group Resistance”, GeoFlorida 2010, Advances in Analysis, Modeling and Design, Geotechnical Special Publication No. 199, ASCE, pp1563-1572.

Siegel, T.C. and NeSmith, W.M. (2010). “Large-Scale Plate Load Testing of Ground Improvement Using Displacement Grout Columns”, GeoFlorida 2010, Advances in Analysis, Modeling and Design, Geotechnical Special Publication No. 199, ASCE, pp2398-2405.

Artistic Construction Photo Contest – Volume 1

Old School (HPL) - R. Thompson

With all of us visiting construction projects across the country, occasionally we take a photo that appears to be somewhat “artistic” – maybe the lighting (or lack of), or the aspect.  I have assembled a few such photos submitted by DBA engineers in the first installment of the DBA Artistic Construction Photo Contest. Included in this installment are such items as: “Daybreak on Night Shift at JJA” and “Fountain” by S. Dapp, the series “Evolution” by P. Axtell, “GI Rig at Sunset” by T. Siegel, and “Piles in the Mist” by R. Thompson.  This first volume has more photos of mine than others, but we’ll work on better balance in future volumes.

Feel free to “vote” for your favorite in the comments.  I’ll try to update periodically as we have more “worthy” photos!

Geo-Florida Presentation by Steve Dapp – Tip-Grouted Drilled Shaft Foundations for the Audubon Bridge

I have uploaded the presentation Steve gave at Geo-Florida 2010 on February 24th.  You can find it on our Presentations page or by clicking the image below.  Enjoy!

 

Pages from Tip Grout Audubon Bridge_Dapp Brown_Geo Florida 2010

 

Audubon Bridge Update – Piers out of the water!

It has been a little while since we last visited the John James Audubon Bridge site in New roads, Louisiana.  My how things have changed!  I just have a couple of pictures of the piers from January – it is really looking like a bridge now!  For frequent updates, check out the webcam and the photo albums on the project web page.  The web cams have a really cool time lapse button that shows you a time lapse loop of the pier from the beginning of construction.

UPDATE (2/28/10) - I added 3 new photos to the slide show that were taken this last week. At that time the piers were at lift 21 and were about elevation +335 feet (the top of the sheet piles at the foundation level are about elevation +50 feet).

DBA on successful St. Louis Bridge team

BridgeImage2009_MS STL mrb-logo

DBA is on the successful team that was awarded the contract for the new Mississippi River Bridge in St. Louis, Missouri.  The project is a joint project of MoDOT/IDOT with MoDOT being the lead agency.  HNTB is the lead bridge designer for the new cable-stayed bridge carrying I-70 over the river.  The bridge is one part of a larger project that also includes the Missouri North I-70 Interchange, the Illinois I-70 Connection, and the Illinois Tri-level Exchange.

From the project web site:

The $640 million Mississippi River Bridge project is proceeding through design, with construction scheduled to start in early 2010. The new Mississippi River Bridge is the first bridge built connecting downtown St. Louis and southwestern Illinois in more than 40 years. Currently, the only urban interstate bridge between Illinois and Missouri is the Poplar Street Bridge, known locally as the PSB. The PSB is one of two bridges in the United States that carry three interstates. By relocating one interstate (I-70) from the Poplar Street Bridge to the new Mississippi River Bridge, drivers will experience less congestion, fewer crashes and less unnecessary fuel use.

The new Mississippi River Bridge will be a 1,500 foot cable-stayed bridge across the Mississippi River between Metro East and St. Louis, Missouri. The bridge is two lanes in each direction, but is wide enough to be restriped for three lanes in each direction if traffic volumes warrant and additional funding is secured. In addition, the bridge project includes approaches on the Illinois and Missouri sides to get traffic to the bridge.

The wining contractor team is Massman/Traylor Brothers/Alberici Constructors.  DBA’s role was to help prepare an alternate concept for the drilled shaft foundation design which will include load test measurements.  We anticipate construction to begin in March with load test shaft.

An overview of the bridge is here.  The press release for the award of the main bridge is here.

logo-massman logo-traylor alberici

Characterization of Loess for Deep Foundations

loess map

 

I have added a recent paper that Dan and Steve contributed to concerning loess that is in the November, 2009 issue of the DFI Journal.  The paper describes the results of site investigation and laboratory tests at a site in Kansas with loess deposits.  The effectiveness of various correlations between field and laboratory tests and design properties are evaluated.  Steve is currently working on the follow-up paper that evaluates lateral load tests of drilled shafts at the site.

Parson, R.L., Johnson, R.M., Brown, D.A., Dapp, S.D., and Brennan, J.J., 2009. “Characterization of Loess for Deep Foundations”, DFI Journal Volume 3, No. 2, November 2009, Deep Foundations Institute, pp14-24.

kcICON Bridge Paper Added

clip_image002

 

I have added the paper that we wrote and Dan presented at the Deep Foundations Institute 34th Annual Conference on Deep Foundations that was held in Kansas City, MO late last month.  The paper highlights how the design-build process was successful in the design and construction of the large diameter drilled shafts supporting the bridge.  We discuss the installation methods used, the load test program, and how we evaluated the durability of the shale rock sockets under drilling fluid.

You can check out the progress of the bridge at the project website.

Axtell, P.J., Thompson, W.R., and Brown, D.A., 2009. “Drilled Shaft Foundations for the kcICON Missouri River Bridge”, Deep Foundations Institute 34th Annual Conference on Deep Foundations, Conference Proceedings 2009, October 21-23, 2009, Kansas City, Missouri, pp. 3-12.

 

Recent Project Photos – (or) What have we been up to the last few months (Part 1)?…… Drilled Shafts!

If you frequent this blog, you have noticed that posts have been rare the last few months.  That is mostly to my being in the field a lot this summer and very busy on lost of projects.  While that is good, it meant I did not have time for updates.  Below are some slide shows from a few drilled shaft projects we worked on this summer.

 

Garden State Parkway Mullica River Bridge, New Jersey – Test Shaft Installation

Paul took a trip to lovely New Jersey to observe a large diameter test shaft on the Mullica River Bridge.  DBA worked as a consultant for Parsons Brinckerhoff on an 8-foot diameter, 220-foot deep test shaft.  CASE was the drilled shaft contractor and Agate was the general contractor.  DBA consulted on the design of the test shaft program, as well as the use of Self Consolidating Concrete (SCC).

 

 

Drilled Shaft Lateral Load Test Research with the University of Kansas

Paul took a ride out west to Kansas City, Kansas (close to home!) to observe a drilled shaft lateral load test in Wyandotte County, near the Cabela’s store on I-435.  The test is part of ongoing research by the University of Kansas for the Kansas DOT.   DBA was involved in previous research concerning laterally loaded shafts behind MSE walls (see previous post, click here for more information on the project).  This research continues on the same theme of investigating the behavior of laterally loaded shafts socketed into the sedimentary rocks in eastern Kansas.  DBA does not have an active role in this project, just an academic interest. 

 

 

 

Huey P. Long Bridge Improvements, New Orleans, Louisiana – Test Shaft Installation

The Huey P. Long Bridge in New Orleans (built in the 1930s) is undergoing a major rehab and expansion.  The vehicle traffic will increase from 2 9-foot lanes in each direction to 3 11-foot lanes in each direction.  This is a very interesting combined highway and railroad bridge with a fascinating history.  The bridge is actually a private bridge owned by the New Orleans Public Belt Railway (click the link to see some cool photos from the construction of the bridge in the 1930s). The project website is here. 

DBA was consulting with the joint venture building the bridge for the base-grouted drilled shafts under one new pier.  A test-shaft was built and tested with O-cells.  Robert was on site while they excavated the test shaft.  Steve was on site during grouting.

Foundation Drilling article (May 2009): Drilled Shaft Loadtests in Limestone by Dan and Robert

clip_image002

 

The May 2009 issue of Foundation Drilling had an article by Dan and Robert summarizing the recent research on drilled shafts socketed into rock for the Southeast Chapter of ADSC .

The article has been posted to our Publications Page.  The full report is located here, for those looking for a little light reading. 

A test site has been selected for Atlanta in the Piedmont formation.  Check back here or at the project page for updates as things move forward.

 

Nashville site shaft excavation

IMG_0550

 

 

 

 

 

 

 

 

Archives

GeotechSearch.com

DBA Photo Albums

ADSC SE Drilled Shaft Research Project, Lawrenceville, GA Test SiteDBA Honors and Awards
JJA Pictures from Chris Ursery (FIGG)Hastings Bridge Construction
Ownesboro Hospital Ground ImprovementArtistic Construction - Vol 1
JJA Construction 2010LPV-145 Test Piles 2009-2010
DFI 2009JJA Construction - Shaft 3W South Load Test - October 2009
Huey P. Long Bridge Drilled Shafts - October 2009JJA Construction - Pier 2W - September 2009 Photos
Univ Kansas Research - Lateral Load Test on Drilled ShaftsHuey P. Long Bridge, New Orleans - Test Shaft Construction - July 16-19, 2009
GIWW West Closure Complex Test Piles June and July 2009Garden State Parkway Mullica River Bridge - Test Shaft Construction - June 2009