Check out the bottom of my post on June 30th World Record O-Cell Load Test for some updates and new links to recent news articles.
|
||||
|
Check out the bottom of my post on June 30th World Record O-Cell Load Test for some updates and new links to recent news articles.
The manual’s authors are three of the country’s top experts in drilled shaft design and construction: our own Dan A. Brown, Ph.D, P.E. , John P. Turner, Ph.D, P.E. of the University of Wyoming, and Raymond J. Castelli, P.E. of Parsons Brinckerhoff. As with any major FHWA publication such as this, there was significant industry involvement in the review process through various technical committees and individuals from ADSC, DFI, and Geo-Institute. A note from Dan:
Dan and John have been using the material in the NHI course this fiscal year, having done some pilot courses the previous year. Some NHI courses, including the Drilled Shaft course, can be hosted by non-government groups. There are also some public seats available occasionally at DOT hosted courses. The NHI catalog page for this course is here. Download Drilled Shafts:Construction Procedures and LRFD Design Methods, 2010. Also linked on our Publications page. Update (7/12/10): For those that prefer the feel of a printed volume in their hands, the ADSC: The International Association of Foundation Drilling will be the distributor of the printed volume of the manual through their Technical Library. It will be available soon, according to ADSC. We’ll post about it as soon as it is available. Update 2 (8/19/10): The printed manual is now available. DBA was part of foundation engineering and construction history while participating in a drilled shaft load test for the New I-70 Mississippi River Bridge in St. Louis, Missouri. A new O-cell world record of 36,000 tons (bi-directional) was achieved on the test, besting the former record of just under 32,000 tons set in 2005 in Korea (see here). The test shaft was built by MTA (a joint venture of Massman/Traylor Brothers/Alberici Constructors) as part of an Alternative Technical Concept (ATC) that MTA submitted in their winning bid. During the bid phase, the owner allowed ATC’s to be submitted by pre-qualified teams. These ATC’s were unique to the team that submitted them (e.g., each team was allowed to submit their own ATC’s if they desired, but the ATC’s were not shared amongst all the teams). DBA worked with MTA to develop an ATC that optimized the drilled shaft foundations shown in the “baseline” drawings provided by the owner. That ATC provided a more economical foundation solution that was accepted, bid, and awarded (note MTA also had the option of bidding the “baseline” drawings as-is). A full-scale load test on a dedicated test shaft using the Osterberg Cell (O-cell) test method was included in the ATC to: 1) prove the design values used for the resistance in the rock socket; and (2) take advantage of higher resistance factors for using a load tests as opposed to only calculations. The baseline drawings did not include a load test. Loadtest, Inc. performed the load test. The bottom-up static load test applied slightly greater than 36,000 tons (bi-directional) to the shaft resulting in about 1/8in of upward movement of the shaft and about the same magnitude of downward displacement at the base. The rock socket was about 23ft deep and 11ft in diameter in very hard limestone. Four 34in O-cells placed at the base of the shaft were loaded to 150% of their rated capacity to achieve the record load. UPDATE (8/4/10): The bridge was featured in the July 2010 issue of Civil Engineering magazine from ASCE in the “News” section. Follow the link below and then go to Page 30. UPDATE (8/17/10): Press Release from MTA (contractor joint venture). UPDATE (8/18/10): ENR.com Article As geotechnical/foundation engineers, we don’t usually get to see much of what happens on a project after the foundations are completed, especially a project like a large bridge that can take years to complete. Technology such as the Internet, webcams, and digital photography have made it easy for us to see how things are progressing on projects, as well as maybe get images of the completed structure. As I have noted before, some projects are using Twitter and Facebook to keep the public informed on closures, delays or overall project progress as part of good public relations. Her are some updates on a few of our recent projects.
The main span is well underway, including the cables. The kcICON Facebook page is here.
Check out the webcam. You can download images if you like. YOu can also do a time-lapse from Day 1 of construction.
Beck Street Bridge: Part of the I-15 Express Link project in Salt Lake City, UT. The photos below I obtained from the photos page on the project web site. We were involved in the design and construction of the foundations for the Beck Street Bridge only.
Papers by Dan, Steve, and Tim that were included in the GeoFlorida 2010 conference have been uploaded to our Publications page. Dan and Steve co-authored a paper on the test program of the base grouted drilled shafts for the Audubon Bridge. Tim co-authored a paper with Willie NeSmith of Berkel and Company Contractors, Inc. on plate load testing of displacement grout columns. Dan was also a co-author with several others on a paper on jet grouting for improved pile lateral capacity.
With all of us visiting construction projects across the country, occasionally we take a photo that appears to be somewhat “artistic” – maybe the lighting (or lack of), or the aspect. I have assembled a few such photos submitted by DBA engineers in the first installment of the DBA Artistic Construction Photo Contest. Included in this installment are such items as: “Daybreak on Night Shift at JJA” and “Fountain” by S. Dapp, the series “Evolution” by P. Axtell, “GI Rig at Sunset” by T. Siegel, and “Piles in the Mist” by R. Thompson. This first volume has more photos of mine than others, but we’ll work on better balance in future volumes. Feel free to “vote” for your favorite in the comments. I’ll try to update periodically as we have more “worthy” photos! The Spring 2010 issue of Deep Foundations from the Deep Foundations Institute includes an article by Dan and Paul (with a little help from yours truly!). The article is based on our paper presented by Dan at the 34th DFI Conference on Deep Foundations last October in Kansas City. The kcICON project continues to roll along. Check out their Facebook page where they have lots of photos and links to their YouTube page. They recently completed the widest bridge deck pour ever for MoDOT. Go to our Publications page to see the article, or click the image below.
I have uploaded the presentation Steve gave at Geo-Florida 2010 on February 24th. You can find it on our Presentations page or by clicking the image below. Enjoy!
It has been a little while since we last visited the John James Audubon Bridge site in New roads, Louisiana. My how things have changed! I just have a couple of pictures of the piers from January – it is really looking like a bridge now! For frequent updates, check out the webcam and the photo albums on the project web page. The web cams have a really cool time lapse button that shows you a time lapse loop of the pier from the beginning of construction. UPDATE (2/28/10) - I added 3 new photos to the slide show that were taken this last week. At that time the piers were at lift 21 and were about elevation +335 feet (the top of the sheet piles at the foundation level are about elevation +50 feet).
DBA is on the successful team that was awarded the contract for the new Mississippi River Bridge in St. Louis, Missouri. The project is a joint project of MoDOT/IDOT with MoDOT being the lead agency. HNTB is the lead bridge designer for the new cable-stayed bridge carrying I-70 over the river. The bridge is one part of a larger project that also includes the Missouri North I-70 Interchange, the Illinois I-70 Connection, and the Illinois Tri-level Exchange. From the project web site:
The wining contractor team is Massman/Traylor Brothers/Alberici Constructors. DBA’s role was to help prepare an alternate concept for the drilled shaft foundation design which will include load test measurements. We anticipate construction to begin in March with load test shaft. An overview of the bridge is here. The press release for the award of the main bridge is here. |
||||
|
Copyright © 2010 Dan Brown and Associates, PLLC - All Rights Reserved |
||||