Get the New FHWA Drilled Shaft Manual

Dan’s Speaking Schedule

September 21-23, 2010 - NHI Drilled Shaft Course, Iowa

October 5-6, 2010 - 42nd STGEC, Charleston, West Virginia

October 14-15, 2010 - DFI 35th Conference on Deep Foundations, Hollywood, California

October 19-21, 2010 - - NHI Drilled Shaft Course, Iowa

November 10, 2010 - ADSC Drilled Shaft Seminar, New York, New York

December 1-2, 2010 - TRB 27th Bridge Conference, San Antonio, Texas

Other DBA Team Speaking Appearences

Tim Siegel (Sept 30-Oct 1, 2010): North Carolina ASCE Section Annual Meeting, Asheville, NC

Robert Thompson (October 5-6, 2010):42nd STGEC, Charleston, West Virginia

Tim Siegel (October 29, 2010): Deep Foundation Design - Axial Capacity, Settlement, and Lateral Resistance, Norfolk, Virginia

Tim Siegel (December 16, 2010): Shallow Foundation Design, Atlanta, Georgia

Steve Dapp (January 11, 2011): 2011 Louisiana Transportation Conference, Baton Rouge, Louisiana

Conferences, Meetings, Seminars, Workshops

DBA on team for New Hastings, MN Bridge

Hastings rendering 2

L-A-PTG logo The Lunda/Ames design-build joint venture (Lunda Construction Company of Black River Falls, Wisconsin and Ames Construction, Inc. of Burnsville, Minnesota) has been awarded a contract to build the new Highway 61 Hastings Bridge over the Mississippi River in Hastings, Minnesota. Parsons Transportation Group is the designer and DBA is performing geotechnical design of the bridge foundations and settlement mitigation as a sub-consultant to PTG.

Here is the exisiting bridge that is being replaced (viewing from upstream):

In addition to several relatively large approach spans, the new bridge will include a 545ft long free-standing arch main span with four lanes of traffic and a 12 foot wide common use pedestrian/bike path. The new bridge will allow additional parking and an artistic plaza area south of the river. An anti-icing system will be installed to help achieve the 100-year design life.

On the south side of the Mississippi River, the bridge foundations will consist of spread footings bearing on dolostone bedrock. The remaining bridge foundations will utilize 42in diameter pipe piles. Several Statnamic load tests, both axial and lateral, will be performed by our friends at AFT.

Settlement mitigation is required beneath the North Embankment due to several relatively thick and deep strata of compressible fine-grained soils. The embankment will also be heavily instrumented to evaluate performance of the embankment and mitigation technique.

Preliminary work including subsurface investigation has begun. The subsurface investigation is being performed by Braun Intertec under sub-contract to DBA. Test piles will be installed in early September, 2010 with subsequent load testing soon after.

The awarded design-build contract is for $120M. The estimated project completion date is May 13, 2013.

DBA Project Page here.

mndotlogo

Mn/DOT Hastings Bridge Project Home Page

Here is a sampling of the local news on the project award:

Hastings Star-Gazette

South Washington County Bulletin

Minneapolis/St. Paul Business Journal

New Project Summaries Added

I have added some new project summaries to our Consulting Projects list.  I have also revised/updated the individual project pages we have, plus the Consulting Projects and Research Projects pages.

The projects I have added are:

image

Beck Street Bridge over I-15, Salt Lake City, Utah

image

Hurricane Protection Projects, New Orleans, Louisiana

I-70 Mississippi River Bridge Test Shaft, St. Louis, Missouri

image

Mullica River Bridge Test Shaft, Port Republic, New Jersey

Bridge updates – kcICON, Audubon, Beck Street

As geotechnical/foundation engineers, we don’t usually get to see much of what happens on a project after the foundations are completed, especially a project like a large bridge that can take years to complete.  Technology such as the Internet, webcams, and digital photography have made it easy for us to see how things are progressing on projects, as well as maybe get images of the completed structure.  As I have noted before, some projects are using Twitter and Facebook to keep the public informed on closures, delays or overall project progress as part of good public relations.  Her are some updates on a few of our recent projects.

 

kcICON:

The main span is well underway, including the cables.  The kcICON Facebook page is here.

PASEOBSOimage10-05-17_16-20-11-00 PASEOBWEimage10-05-04_07-40-00-43

 

Audubon Bridge:

Check out the webcam.  You can download images if you like.  YOu can also do a time-lapse from Day 1 of construction.

image image

 

Beck Street Bridge:

Part of the I-15 Express Link project in Salt Lake City, UT.   The photos below I obtained from the photos page on the project web site.  We were involved in the design and construction of the foundations for the Beck Street Bridge only.

5-5-10-03  picture-123-scopy_0_picture-158-s

Geo-Florida 2010 Papers posted

geoflorida2010 logo

 

Audubon graph-GeoFlorida-Dapp

 

Papers by Dan, Steve, and Tim that were included in the GeoFlorida 2010 conference have been uploaded to our Publications page.  Dan and Steve co-authored a paper on the test program of the base grouted drilled shafts for the Audubon Bridge.  Tim co-authored a paper with Willie NeSmith of Berkel and Company Contractors, Inc. on plate load testing of displacement grout columns.  Dan was also a co-author with several others on a paper on jet grouting for improved pile lateral capacity.

 

Dapp, S.D. and Brown, D.A. (2010). “Evaluation of Base Grouted Drilled Shafts at the Audubon Bridge”, GeoFlorida 2010, Advances in Analysis, Modeling and Design, Geotechnical Special Publication No. 199, ASCE, pp1553-1562.

Rollins, K.M., Herbst, M., Adsero, M. and Brown, D.A. (2010) “Jet Grouting and Soil Mixing for Increased Lateral Pile Group Resistance”, GeoFlorida 2010, Advances in Analysis, Modeling and Design, Geotechnical Special Publication No. 199, ASCE, pp1563-1572.

Siegel, T.C. and NeSmith, W.M. (2010). “Large-Scale Plate Load Testing of Ground Improvement Using Displacement Grout Columns”, GeoFlorida 2010, Advances in Analysis, Modeling and Design, Geotechnical Special Publication No. 199, ASCE, pp2398-2405.

Artistic Construction Photo Contest – Volume 1

Old School (HPL) - R. Thompson

With all of us visiting construction projects across the country, occasionally we take a photo that appears to be somewhat “artistic” – maybe the lighting (or lack of), or the aspect.  I have assembled a few such photos submitted by DBA engineers in the first installment of the DBA Artistic Construction Photo Contest. Included in this installment are such items as: “Daybreak on Night Shift at JJA” and “Fountain” by S. Dapp, the series “Evolution” by P. Axtell, “GI Rig at Sunset” by T. Siegel, and “Piles in the Mist” by R. Thompson.  This first volume has more photos of mine than others, but we’ll work on better balance in future volumes.

Feel free to “vote” for your favorite in the comments.  I’ll try to update periodically as we have more “worthy” photos!

kcICON Bond Bridge Article in Deep Foundations Magazine

The Spring 2010 issue of Deep Foundations from the Deep Foundations Institute includes an article by Dan and Paul (with a little help from yours truly!).  The article is based on our paper presented by Dan at the 34th DFI Conference on Deep Foundations last October in Kansas City.

The kcICON project continues to roll along.  Check out their Facebook page where they have lots of photos and links to their YouTube page.  They recently completed the widest bridge deck pour ever for MoDOT.

Go to our Publications page to see the article, or click the image below.

 

kcICON DF mag article

Geo-Florida Presentation by Steve Dapp – Tip-Grouted Drilled Shaft Foundations for the Audubon Bridge

I have uploaded the presentation Steve gave at Geo-Florida 2010 on February 24th.  You can find it on our Presentations page or by clicking the image below.  Enjoy!

 

Pages from Tip Grout Audubon Bridge_Dapp Brown_Geo Florida 2010

 

Audubon Bridge Update – Piers out of the water!

It has been a little while since we last visited the John James Audubon Bridge site in New roads, Louisiana.  My how things have changed!  I just have a couple of pictures of the piers from January – it is really looking like a bridge now!  For frequent updates, check out the webcam and the photo albums on the project web page.  The web cams have a really cool time lapse button that shows you a time lapse loop of the pier from the beginning of construction.

UPDATE (2/28/10) - I added 3 new photos to the slide show that were taken this last week. At that time the piers were at lift 21 and were about elevation +335 feet (the top of the sheet piles at the foundation level are about elevation +50 feet).

Foothills Parkway Bridge No. 2 – Smokey Mountains, Tennessee

image

DBA is the geotechnical engineer for a pre-cast post-tensioned segmental concrete bridge that is part of what is called the “missing link” in the Foothills Parkway (see background information below) near the Great Smokey Mountains National Park. The National Park Service has awarded a design/build contract to Bell & Associates Highway Construction of Brentwood, TN. VSL will cast and erect the post-tensioned segmental bridge. The lead bridge designer is Corven Engineering, Inc. of Tallahassee, FL. Palmer Engineering in Nashville, TN will be the structural/civil engineer for the project. Some design work was begun by FHWA Eastern Federal Lands Division in the 1990’s but was never completed and let for bid due to lack of funding. The process to complete the “missing link” has begun again using the design/build delivery system.

Since the purpose of the Parkway is to provide scenic views of the mountains and valleys, the project has strict requirements to minimize disturbance. In addition to special design and construction techniques (to be discussed in a later post after design is complete), Bell included significant attention to landscaping and site preservation. Hedstrom Design of Knoxville, TN is the landscape architect for the project, providing services key to minimizing impact on the site from construction activities, as well as providing a finished look to the the project that blends with the surrounding landscape.

Design work is well under way and Bell has started work at the site. The bridge is scheduled to be completed by November, 2011 – a very tight schedule!

A local news article about the project award is here in the Cherokee One Feather.

Click on the image to see a map of the Parkway (Source: Briefing Statement linked below):

FHP Map 1998_s

Background information on the Parkway and the “Missing Link”:

Congress authorized the Foothills Parkway as a scenic parkway on February 22, 1944 (Public Law 232). The stated purpose of the Parkway is to provide beautiful vistas of the Great Smoky Mountains along their northern flank (TN) and to disperse traffic in the area. The entire 72-mile corridor is administered by Great Smoky Mountains National Park. To date, two discontinuous segments totaling 22.5 miles are completed and open. The Parkway parallels the Park’s northern boundary from Chilhowee Lake, TN (Section 8H) to I-40 near Cosby, TN (Section 8A).

Between 1966 and 1970, a 6.4-mile section of road between U.S. Highway 321 in Walland and Carr Creek (Section 8F), was constructed. In the 1980s, two contracts were awarded for construction of approximately 10 miles of road (Section 8E). Both projects experienced structural fill failures and erosion problems that caused the projects to be suspended in 1989, thus leaving a 1.65-mile segment uncompleted around Caylor Gap which is referred to as the “missing link.” In the 1990s, a new design was developed by the Federal Highway Administration (FHWA) to complete the “missing link” using bridges, walls, and fills to minimize surface disturbance and environmental impacts.

Source: Briefing Statement, Great Smokey Mountains National Park, Completion of the Foothills Parkway, May 2009

Bell vsl_logo Corven eng

DBA on successful St. Louis Bridge team

BridgeImage2009_MS STL mrb-logo

DBA is on the successful team that was awarded the contract for the new Mississippi River Bridge in St. Louis, Missouri.  The project is a joint project of MoDOT/IDOT with MoDOT being the lead agency.  HNTB is the lead bridge designer for the new cable-stayed bridge carrying I-70 over the river.  The bridge is one part of a larger project that also includes the Missouri North I-70 Interchange, the Illinois I-70 Connection, and the Illinois Tri-level Exchange.

From the project web site:

The $640 million Mississippi River Bridge project is proceeding through design, with construction scheduled to start in early 2010. The new Mississippi River Bridge is the first bridge built connecting downtown St. Louis and southwestern Illinois in more than 40 years. Currently, the only urban interstate bridge between Illinois and Missouri is the Poplar Street Bridge, known locally as the PSB. The PSB is one of two bridges in the United States that carry three interstates. By relocating one interstate (I-70) from the Poplar Street Bridge to the new Mississippi River Bridge, drivers will experience less congestion, fewer crashes and less unnecessary fuel use.

The new Mississippi River Bridge will be a 1,500 foot cable-stayed bridge across the Mississippi River between Metro East and St. Louis, Missouri. The bridge is two lanes in each direction, but is wide enough to be restriped for three lanes in each direction if traffic volumes warrant and additional funding is secured. In addition, the bridge project includes approaches on the Illinois and Missouri sides to get traffic to the bridge.

The wining contractor team is Massman/Traylor Brothers/Alberici Constructors.  DBA’s role was to help prepare an alternate concept for the drilled shaft foundation design which will include load test measurements.  We anticipate construction to begin in March with load test shaft.

An overview of the bridge is here.  The press release for the award of the main bridge is here.

logo-massman logo-traylor alberici

Archives

GeotechSearch.com

DBA Photo Albums

Artistic Construction - Vol 1JJA Construction 2010
LPV-145 Test Piles 2009-2010DFI 2009
JJA Construction - Shaft 3W South Load Test - October 2009Huey P. Long Bridge Drilled Shafts - October 2009
JJA Construction - Pier 2W - September 2009 PhotosUniv Kansas Research - Lateral Load Test on Drilled Shafts
Huey P. Long Bridge, New Orleans - Test Shaft Construction - July 16-19, 2009GIWW West Closure Complex Test Piles June and July 2009
Garden State Parkway Mullica River Bridge - Test Shaft Construction - June 2009JJA Construction - Base Grouting and Other Construction - June 2009
JJA Construction - Shaft Excavation, PIle Driving, and Cofferdams - May 2009JJA Construction - East Pier and East High Approach - April 2009
KcICON River Bridge - Bent 1, Bent 5, and Pylon - March 2009JJA Construction - West Pier and West High Approach Shafts - April 2009