Get the New FHWA Drilled Shaft Manual
Get the NCHRP Synthesis 418 – Pile Criteria From Test Pile Data
Dan’s Speaking Schedule September 12-13, 2012: Concrete used in Drilled Shaft Construction - ADSC/DFI Drilled Shaft Seminar - Denver, Colorado
October 26, 2012: Factors Affecting the Selection and Use of Drilled Shafts for Transportation Infrastructure Projects - 26th Central Pennsylvania Geotechnical Conference - ASCE/DFI - Hershey, Pennsylvania
Other DBA Team Speaking Appearances John Turner (September 12-13, 2012): Analysis & Design of Drilled Shafts - ADSC/DFI Drilled Shaft Seminar - Denver, Colorado
John Turner (September 12-13, 2012): Techniques for Drilled Shaft Construction - ADSC/DFI Drilled Shaft Seminar - Denver, Colorado
Conferences, Meetings, Seminars, Workshops
|
By David Graham, on November 9th, 2011

As massive concrete piers rise from the Mississippi river in southeast Minnesota, people have begun to take notice of what will become the longest free-standing tied-arch bridge in North America. A unique project in several respects, the new Hasting bridge has recently been featured in articles on the websites of ENR and Roads & Bridges. The ENR article is a republication of an article that originally appeared in the Minneapolis Star Tribune highlighting the construction process of the last year, with particular focus on the process of constructing the river piers. The Roads & Bridges article is a more technically in-depth piece written by the lead bridge engineer Vincent T. Gastoni, P.E., of Parsons Transportation Group. Both articles discuss some of the many geotechnical changes faced on this project. This excerpt from Roads & Bridges is a concise description of the pier foundations and some of the reasoning behind their selection:
The main river piers are concrete delta-style frames with the tied-arch superstructure fully framed into the pier through the knuckle connection. The stiffness of the foundation system was then integral to the overall force effects in the structure. The north pier is located in 190 ft of soft soils overlaying rock and supported on unfilled 42-in. driven steel pipe piles. Drilled shafts were investigated early but were not cost-effective, impacted the schedule and presented a risk to the existing bridge due to potential caving effects. Statnamic pile load testing was used to validate the vertical capacity and lateral performance of the 42-in. piles. The south pier footing is close to the rock surface; however, the rock was deeper, more sloped than expected, and the originally planned spread footing was changed to short drilled shafts during the final design. Dan Brown & Associates provided the team with geotechnical analysis and recommendations.
Our Tim Siegel pointed out that the statement “It’s a marvel of engineering that requires ingenious construction techniques, most of which are invisible to the drivers whizzing by overhead,” from the Star Tribune, is an accurate description of how our work as foundation designers and constructors is often viewed. Although much of the ingenuity and innovation that goes into the geotechnical aspects of projects often goes unnoticed by the general public, it is certainly refreshing to see articles like these. For us at DBA, it is even more refreshing to see our efforts credited by name as they were in the article by Vince when he wrote, “Dan Brown & Associates provided the team with geotechnical analysis and recommendations.”
For a design-build project with so many different geotechnical components (driven piles, drilled shafts, spread footings, retaining walls, a column-supported embankment, and light weight fill), it is hard to believe that our role as the lead geotechnical engineer is nearing completion just a little over a year after construction began. At this point, the only foundations that have yet to be constructed are some of the rock bearing spread footings at the south approach. DBA will also monitor instrumentation installed in the column-supported embankment for the next two years.
Previous blog posts by Aaron and David can be found here:Hastings Bridge Update and Hastings Update and Photo Album. Additional information can be found on the DBA project page here.
By Robert Thompson, on August 25th, 2011
Tim has authored a Technical Note in the most recent issue (June 2011) of the DFI Journal. The note is entitled “Simplified Settlement Model for a Shallow Foundation on Composite Ground with Rigid Piles”. From the Abstract:
A piled raft refers to a shallow foundation that is structurally connected to the piles, while composite ground refers to a soil-pile matrix where the piles are not structurally connected. The design objectives for both a piled raft and composite ground are (excluding special considerations such as expansive soil): (1) to provide a sufficient ultimate resistance and (2) to distribute the load into the soil-pile matrix so that the settlement experienced by the shallow foundation is within tolerable limits. A simplified model is proposed for a shallow foundation on composite ground where the foundation settlement is estimated as the sum of the downward movement of the piles plus the downward movement of the shallow foundation relative to the pile head. The proposed simplified model is applied using conventional geotechnical analyses for two hypothetical examples of shallow foundations undergoing compression settlement.
This paper was originally published in DFI’s bi-annual journal, Volume 5, No. 1 in June 2011. DFI is an international technical association of firms and individuals involved in the deep foundations and related industry. The DFI Journal is a member publication. To join DFI and receive the journal, go to www.dfi.org for further information. ”
You can also subscribe to the DFI Journal here.
By David Graham, on April 1st, 2011

Well, I, David, have survived my first (and hopefully last) winter in Minnesota. I spent most of January and February observing the installation of the Pier 5 drilled shafts at the new Hastings bridge project in Hastings, Minnesota. In addition to the drilled shafts, there has been a lot activity at Hastings since Aaron last blogged about this project in January. A link to his post is here. All of the ground improvement piles for the column-supported embankment have been installed and approximately 75% of the caps have been poured. The 42-inch piles and pile caps for Piers 8, 9, and 10 are also complete. Piles for the north embankment retaining wall have been installed and construction of the wall has begun. Excavation for the rock bearing spread footings that will support the south land piers is in progress. Work at Piers 6 and 7 and on the north shore are currently on hold as the Mississippi River is experiencing its annual spring flood. The water level is about 14 feet above normal elevation.
I have taken the pictures Paul and I have collected over the last few months and uploaded some of the more interesting ones to a Picasa web album. The pictures are generally in chronological order and cover most of the construction process from November of 2010 right up to the end of March 2011. A link to our our video of a Statnamic load test at Hastings that Aaron blogged about is here.
By David Graham, on January 17th, 2011
Last spring, DBA designed a composite ground improvement system for a new hospital as part of the Owensboro, Kentucky, Medical Health System. Tim performed most of the ground improvement design for the design-build project with Berkel & Company Contractors, Inc. The design is a composite ground system with a layer of compacted gravel above lightly reinforced cast-in-placed displacement piles (known commercially as CGEs). Spread foundations placed on the compacted gravel distribute the structural load to the soil and CGEs. The construction of the composite ground system began and was completed in the summer of 2010. The project has a designated webcam that allows the public to view the entire construction process. The webcam can be viewed here. We have also uploaded some photos of construction and testing of the CGEs here.
By Robert Thompson, on December 8th, 2010
A paper by Paul Axtell and others on shear strength of cement-bentonite grout mixes has been added to our Publications Page.

Axtell, P.J., Stark, T.D., and Dillon, J.C. (2010). “Peak and Post-Peak Shear Strength of Cement-Bentonite”, DFI Journal Volume 4, No. 1, August 2010, Deep Foundations Institute, pp59-65.
By Robert Thompson, on May 11th, 2010

Papers by Dan, Steve, and Tim that were included in the GeoFlorida 2010 conference have been uploaded to our Publications page. Dan and Steve co-authored a paper on the test program of the base grouted drilled shafts for the Audubon Bridge. Tim co-authored a paper with Willie NeSmith of Berkel and Company Contractors, Inc. on plate load testing of displacement grout columns. Dan was also a co-author with several others on a paper on jet grouting for improved pile lateral capacity.
Dapp, S.D. and Brown, D.A. (2010). “Evaluation of Base Grouted Drilled Shafts at the Audubon Bridge”, GeoFlorida 2010, Advances in Analysis, Modeling and Design, Geotechnical Special Publication No. 199, ASCE, pp1553-1562.
Rollins, K.M., Herbst, M., Adsero, M. and Brown, D.A. (2010) “Jet Grouting and Soil Mixing for Increased Lateral Pile Group Resistance”, GeoFlorida 2010, Advances in Analysis, Modeling and Design, Geotechnical Special Publication No. 199, ASCE, pp1563-1572.
Siegel, T.C. and NeSmith, W.M. (2010). “Large-Scale Plate Load Testing of Ground Improvement Using Displacement Grout Columns”, GeoFlorida 2010, Advances in Analysis, Modeling and Design, Geotechnical Special Publication No. 199, ASCE, pp2398-2405.
|
|
|