Get the New FHWA Drilled Shaft Manual
Get the NCHRP Synthesis 418 – Pile Criteria From Test Pile Data
Dan’s Speaking Schedule March 16, 2012 - "Advanced" Design and Construction Issues with Drilled Shaft Foundations; Case Histories - ADSC Equipment EXPO and Technical Conference - San Antonio, Texas
March 26-28, 2012 - State of the Art and Practice for Drilled Foundations - GeoCongress 2012 - ASCE/Geo-Institute - San Francisco, California
Other DBA Team Speaking Appearences Tim Siegel (January 22, 2012): Innovative Techniques for Characterizing Karst Terrain, Workshop on Geo-innovation in Subsurface Exploration, TRB Annual Meeting, Washington, D.C.
John Turner and Robert Thompson (February 21-23, 2012): NHI Drilled Shaft Course - Kansas DOT, Topeka, Kansas
Robert Thompson (February 24, 2012): Conservatism in Drilled Shaft Design When
Utilizing Rock Sockets, Alabama Transportation Conference, Montgomery, Alabama
Tim Siegel (March 15, 2012): Micropile Design Installation and Performance for the Foothills Parkway, ADSC Equipment EXPO and Technical Conference, San Antonio, Texas
Robert Thompson (March 15, 2012): Full-Scale Load Tests on Drilled Shafts in Tennessee and Georgia, ADSC Equipment EXPO and Technical Conference, San Antonio, Texas
Erik Loehr (March 15, 2012): Slope Stabilization Using Micropiles, ADSC Equipment EXPO and Technical Conference, San Antonio, Texas
TBA (April 10-12, 2012): NHI Drilled Shaft Course - South Carolina DOT, Columbia, South Carolina
Conferences, Meetings, Seminars, Workshops
|
By Robert Thompson, on February 2nd, 2012
The report for the ADSC Southeast Chapter Lawrenceville, Georgia Test Site is complete and published (link below).
This is the second report from their research project on rock-socketed drilled shafts in the Southeast U.S. This report is from the Lawrenceville, Georgia test site where shafts constructed in metamorphic rock of the Piedmont geologic province were load tested using the O-Cell load test device. The report link is below. Additional information about the test site can be found at the Lawrenceville Site Page.
The first site of this project was in Nashville, Tennessee where shafts constructed in limestone were tested. Information on the Nashville Site and the test reports can be found at the Nashville Site Page.
Both reports will be the feature of a paper and presentation by Robert at the 2012 ADSC Expo, March 13-17, in San Antonio, TX. More information about the Expo can be found here.
Thompson, W.R., Brown, D.A., and Hudson, A.B. (2012). “Load Testing of Drilled Shaft Foundations in Piedmont Rock, Lawrenceville, GA, Report for ADSC Southeast Chapter, January, 2012.
By Robert Thompson, on January 24th, 2012
The drilled shaft foundations for the new I-70 Mississippi River Bridge in St. Louis, MO are the subject of two recent papers written by Paul and Dan and published by DFI. Dan presented the paper focusing on the Alternate Technical Concept (ATC) process at the DFI 36th Annual Conference in October. (previous post here). A case history paper by Paul and Dan was published last month in Volume 5, Number 2 of the DFI Journal. Links to the papers are below, as well as on our Publications page. Other posts on this bridge are here.
Brown, D.A., Axtell, P.J., and Kelley, J. (2011). “The Alternate Technical Concept Process for the Foundations at the New Mississippi River Bridge, St. Louis”, Proceedings of the 36th Annual Conference on Deep Foundations, 2011, Boston, MA, USA, pp171-177.
This paper was originally published in the Proceedings of the 36th Annual Conference on Deep Foundations, the 2011 annual meeting of DFI. Go to www.dfi.org to purchase the procedings or for further information.
Axtell, P.J. and Brown, D.A. (2011). “Case History – Foundations for the New Mississippi River Bridge – St.Louis”, DFI Journal Volume 5, Number 2, December 2011, Deep Foundations Institute, pp3-15.
This paper was originally published in DFI’s bi-annual journal, Volume 5, No. 2 in December 2011. DFI is an international technical association of firms and individuals involved in the deep foundations and related industry. The DFI Journal is a member publication. To join DFI and receive the journal, go to www.dfi.org for further information.
By David Graham, on November 9th, 2011

As massive concrete piers rise from the Mississippi river in southeast Minnesota, people have begun to take notice of what will become the longest free-standing tied-arch bridge in North America. A unique project in several respects, the new Hasting bridge has recently been featured in articles on the websites of ENR and Roads & Bridges. The ENR article is a republication of an article that originally appeared in the Minneapolis Star Tribune highlighting the construction process of the last year, with particular focus on the process of constructing the river piers. The Roads & Bridges article is a more technically in-depth piece written by the lead bridge engineer Vincent T. Gastoni, P.E., of Parsons Transportation Group. Both articles discuss some of the many geotechnical changes faced on this project. This excerpt from Roads & Bridges is a concise description of the pier foundations and some of the reasoning behind their selection:
The main river piers are concrete delta-style frames with the tied-arch superstructure fully framed into the pier through the knuckle connection. The stiffness of the foundation system was then integral to the overall force effects in the structure. The north pier is located in 190 ft of soft soils overlaying rock and supported on unfilled 42-in. driven steel pipe piles. Drilled shafts were investigated early but were not cost-effective, impacted the schedule and presented a risk to the existing bridge due to potential caving effects. Statnamic pile load testing was used to validate the vertical capacity and lateral performance of the 42-in. piles. The south pier footing is close to the rock surface; however, the rock was deeper, more sloped than expected, and the originally planned spread footing was changed to short drilled shafts during the final design. Dan Brown & Associates provided the team with geotechnical analysis and recommendations.
Our Tim Siegel pointed out that the statement “It’s a marvel of engineering that requires ingenious construction techniques, most of which are invisible to the drivers whizzing by overhead,” from the Star Tribune, is an accurate description of how our work as foundation designers and constructors is often viewed. Although much of the ingenuity and innovation that goes into the geotechnical aspects of projects often goes unnoticed by the general public, it is certainly refreshing to see articles like these. For us at DBA, it is even more refreshing to see our efforts credited by name as they were in the article by Vince when he wrote, “Dan Brown & Associates provided the team with geotechnical analysis and recommendations.”
For a design-build project with so many different geotechnical components (driven piles, drilled shafts, spread footings, retaining walls, a column-supported embankment, and light weight fill), it is hard to believe that our role as the lead geotechnical engineer is nearing completion just a little over a year after construction began. At this point, the only foundations that have yet to be constructed are some of the rock bearing spread footings at the south approach. DBA will also monitor instrumentation installed in the column-supported embankment for the next two years.
Previous blog posts by Aaron and David can be found here:Hastings Bridge Update and Hastings Update and Photo Album. Additional information can be found on the DBA project page here.
By Robert Thompson, on November 2nd, 2011

Dan and Steve co-authored an article in the Fall 2011 issue of Deep Foundations (from DFI) that covered the foundations for the recently completed record-setting Audubon Bridge in Louisiana. Dan and Steve cover not only the shaft testing, design, and construction, but also the unique cofferdam used for the tower foundations. I recently highlighted an article by Sereno Brown, P.E. of Flatiron that covered the design and installation of the cofferdam in detail.
You can receive Deep Foundations every quarter (soon bi-monthly!), as well as the DFI Journal, by joining DFI. Get information on joining at this link – click on “Membership” at the top banner.
By Robert Thompson, on October 11th, 2011
During a recent trip to Taiwan, Steve had the opportunity to participate in a lecture on base grouted drilled shaft foundations. He was invited to speak at a meeting of the Chinese Taipei Geotechnical Society (CTGS), also known as the Taiwan Geotechnical Society (TGS), by Dr. Prof. San-Shyan, Lin, National Taiwan Ocean University (current president of TGS). The meeting was held at the National Taiwan University of Science and Technology.
His visit on 21 June 2011 was noted in the August 2011 issue (Volume 5, No. 4, p82) of the ISSMGE Bulletin. During his lecture, Steve talked about the experiences of DBA with base grouting drilled shafts at the Audubon Bridge and the Huey P. Long Bridge on the Mississippi River in Louisiana. Steve said that base grouting has become a very common technology in Taiwan for high rise structures supported on drilled shafts.
The meeting is noted here on the TGS site.

(Source: ISSMGE Bulletin Volume 5, No. 4, p82)
By Robert Thompson, on October 6th, 2011
That’s right load test fans, The results are in! The ADSC Southeast Chapter is proud to announce the “winners” from the prediction contest for the Lawrenceville, GA test site. In the table below, we have listed the winner and their prediction. The winners are the closest to the average measured values as reported by Loadtest, Inc and may not represent the reported maximum values recommended in the final report by DBA. We won’t release the final report until the ASCE Georgia Section Geotechnical Group meeting November 15, 2011 at 6:30pm at the Georgia Power Company’s Headquarters in Atlanta. Dr. Brown will be presenting the findings then – so come to the meeting and get it first, or look to the DBA or ADSC web sites after November 15th to get the report.
|
Shaft
|
Name
|
Prediction
|
|
1 – Unit Base Resistance
|
Gloria Rodgers
(Building and Earth Sciences, Inc.)
|
750 ksf
|
|
1 – Unit Side Resistance
|
Todd Barber (Geo-Hydro Engineers, Inc.)
|
50 ksf
|
|
2 – Unit Base Resistance
|
Todd Barber (Geo-Hydro Engineers, Inc.)
|
690 ksf
|
|
2 – Unit Side Resistance
|
TIE:
Jim Pegues (Southern Company Svcs.)
Tom Scruggs (Georgia DOT)
|
3 ksf
|
By Robert Thompson, on July 31st, 2011

As noted earlier on this blog, the Audubon Bridge opened a little bit earlier than planned. Although over a year old, an article recently came to my attention that puts a spotlight on the unique engineering and construction that went into the cofferdams for the two main bridge piers in the Mississippi River. The article is “John James Audubon Bridge Project – Cofferdam Construction for the Main Span Pier Foundations”, published in the February 2010 issue of Louisiana Civil Engineer, the Journal of the Louisiana Section of the American Society of Civil Engineers.
The article’s lead author, Sereno Brown, P.E., was the construction team’s Project Engineer for the design-build project. In the article, Mr. Brown outlines the issues that led to the team selecting a pre-cast concrete cofferdam over other methods, the design methodology, and then the construction of the cofferdam. The effort posed several significant design and construction challenges, including the sequence of lowering the cofferdam into place through a set of hydraulic jacks. The entire process was truly an amazing engineering and construction feat.
Download the article here.
By Robert Thompson, on July 26th, 2011
Update (7/31/11) – Field Day set for Thursday, August 18th – More info here!
Back by popular demand, we will hold a prediction contest for the second test site in the ADSC drilled shaft research project for rock sockets in the Southeastern U.S. Contestants are encouraged to download the information linked below and then submit their predictions of unit side resistance and base resistance that will be measured by the O-cell tests. The winner will be announced at the field test and demonstration day on site, as well as published in this blog along with all submitted predictions.
Two test shafts will be installed July 26 – 29th at the yard of Foundation Technologies, Inc. One will include a rock socket to attempt to test side and base resistance in the rock socket. The other shaft will be drilled to “rock auger refusal” to attempt to test side resistance in the partially weathered rock (locally termed PWR) and base resistance at “rock auger refusal”. In the Piedmont area, the highly weathered upper rock zone is commonly called PWR. Another common usage is “rock auger refusal” to define where “hard rock” begins. It is thought that designers may be overly conservative with base resistance values at “rock auger refusal”. Hopefully this test will provide useful data in that regard.
Testing will occur during a field demonstration day in mid-August. We’ll post the date once it is finalized.
Information to include the test shaft configurations and exploratory boring data can be downloaded here.
The contest entry form along with instructions for submission can be downloaded here.
We will have Aaron on site to observe and take lots of pictures. We’ll post his photos of the excavations as soon as we can (check the project web page soon after August 1st) to assist in making predictions.
All predictions must be submitted by the close of business, August 12, 2011.
For more information, visit the test site page.
Previous posts.
By David Graham, on July 22nd, 2011

Constructability Considerations When Designing Drilled Shaft Foundations for Bridges
The May/June 2011 issue of ASCE’s Geo-Strata focuses on bridge geotechnics. Dan contributed an article to this issue summarizing key constructability considerations for bridge drilled shaft designers. Specifically, the article focuses on fresh concrete properties and reinforcement design. Discussion of self consolidating concrete (SCC) and column-shaft connections is also included. The article has been added to our publications page and is available through the link above. Additional details related to bridge drilled shaft constructability can be found in the 2010 FHWA Drilled Shaft Manual here.
By Robert Thompson, on July 20th, 2011
The John James Audubon Bridge was opened to traffic on May 10, 2011 a little earlier than planned. While the project is not 100% complete, the bridge was sufficiently complete to allow an emergency opening due to closure of the nearby ferry the bridge is replacing. From the project website:
Due to the high level of the Mississippi River causing the closure of the New Roads/St. Francisville ferry, the Louisiana Department of Transportation and Development (DOTD) opened the John James Audubon Bridge at 10 a.m. on Thursday, May 5, 2011. This emergency opening allowed continuous river-crossing access for traffic affected by the ferry closure. The ferry, which carried approximately 720 vehicles per day according to 2009-2010 DOTD statistics, is permanently closed with the opening of the Audubon Bridge.
Construction is still ongoing and could affect traffic until the project is 100% complete later this year.
|
|
|