Get the New FHWA Drilled Shaft Manual
Get the NCHRP Synthesis 418 – Pile Criteria From Test Pile Data
Dan’s Speaking Schedule September 12-13, 2012: Concrete used in Drilled Shaft Construction - ADSC/DFI Drilled Shaft Seminar - Denver, Colorado
Other DBA Team Speaking Appearances D. Mike Holloway (May 17, 2012): A Driven Pile is a Tested Pile - Not So Fast - DFI SuperPile - Portland, Oregon
John Turner (September 12-13, 2012): Analysis & Design of Drilled Shafts - ADSC/DFI Drilled Shaft Seminar - Denver, Colorado
John Turner (September 12-13, 2012): Techniques for Drilled Shaft Construction - ADSC/DFI Drilled Shaft Seminar - Denver, Colorado
Conferences, Meetings, Seminars, Workshops
|
By Robert Thompson, on July 26th, 2011
Update (7/31/11) – Field Day set for Thursday, August 18th – More info here!
Back by popular demand, we will hold a prediction contest for the second test site in the ADSC drilled shaft research project for rock sockets in the Southeastern U.S. Contestants are encouraged to download the information linked below and then submit their predictions of unit side resistance and base resistance that will be measured by the O-cell tests. The winner will be announced at the field test and demonstration day on site, as well as published in this blog along with all submitted predictions.
Two test shafts will be installed July 26 – 29th at the yard of Foundation Technologies, Inc. One will include a rock socket to attempt to test side and base resistance in the rock socket. The other shaft will be drilled to “rock auger refusal” to attempt to test side resistance in the partially weathered rock (locally termed PWR) and base resistance at “rock auger refusal”. In the Piedmont area, the highly weathered upper rock zone is commonly called PWR. Another common usage is “rock auger refusal” to define where “hard rock” begins. It is thought that designers may be overly conservative with base resistance values at “rock auger refusal”. Hopefully this test will provide useful data in that regard.
Testing will occur during a field demonstration day in mid-August. We’ll post the date once it is finalized.
Information to include the test shaft configurations and exploratory boring data can be downloaded here.
The contest entry form along with instructions for submission can be downloaded here.
We will have Aaron on site to observe and take lots of pictures. We’ll post his photos of the excavations as soon as we can (check the project web page soon after August 1st) to assist in making predictions.
All predictions must be submitted by the close of business, August 12, 2011.
For more information, visit the test site page.
Previous posts.
By Robert Thompson, on July 20th, 2011
The John James Audubon Bridge was opened to traffic on May 10, 2011 a little earlier than planned. While the project is not 100% complete, the bridge was sufficiently complete to allow an emergency opening due to closure of the nearby ferry the bridge is replacing. From the project website:
Due to the high level of the Mississippi River causing the closure of the New Roads/St. Francisville ferry, the Louisiana Department of Transportation and Development (DOTD) opened the John James Audubon Bridge at 10 a.m. on Thursday, May 5, 2011. This emergency opening allowed continuous river-crossing access for traffic affected by the ferry closure. The ferry, which carried approximately 720 vehicles per day according to 2009-2010 DOTD statistics, is permanently closed with the opening of the Audubon Bridge.
Construction is still ongoing and could affect traffic until the project is 100% complete later this year.
By Robert Thompson, on June 27th, 2011
The planned second load test in the ADSC research project for rock sockets in the Southeastern U.S. is moving closer to execution. Bruce Long of Long Foundation Drilling Company provides this update:
To Fellow Load Testers,
We want to thank everyone who submitted questions or comments regarding the preliminary load test program submitted to us by Dr. Dan Brown. Those comments, and more, will be considered while fine-tuning the program.
Because we have several companies donating their time and money, we have to be flexible with respect to the installation and testing dates. We have tentatively selected some dates, but these are subject to change depending upon the workloads of those volunteering their efforts. We hope to begin shaft installation during the last two weeks of July (weeks beginning the 18th or 25th). The actual load testing would probably take place the week of August 8th, with the actual test date being decided upon by sometime in early July (I hope to give everyone at least a 3-4 week notice).
The actual test date would include a field day visit by all interested parties to the test site at Foundation Technologies office in Lawrenceville, GA. Activities will include a load testing discussion led by Dr. Dan Brown, along with lunch. We would then move to the test site where Loadtest, Inc. will be conducting the Osterberg Load Test on our first shaft. A discussion of the testing process and procedures by Loadtest will precede the actual testing (We will be submitting information later regarding a load test contest where each of you will get to predict the outcome of the test with a special prize going to the winner). We also hope to be drilling on the second shaft that day and will be discussing the drill rigs, tools, and other equipment being used, as well as having the other Osterberg cell available for viewing. This site visit proved to be very well received when we did it in Nashville at the last load test. We hope for a big turnout that day.
I wanted to give everybody a brief update and will be in touch when additional information becomes available in the near future. Thank you for your interest, and if anyone has any questions regarding this plan, please feel free to call me at your convenience.
Bruce Long
President
Long Foundation Drilling Co.
Previous post is here.
The test site page is here.
The main page for the research project is here.
By Robert Thompson, on June 13th, 2011

Dr. Erik Loehr, P.E. was honored by the ADSC with the ADSC Outstanding Service Award, presented at the President’s Luncheon at their 2011 annual meeting in New Orleans, Louisiana (Feb 1 –5, 2011). The award recognized Erik’s research in the use of micropiles for slope stabilization and as foundations. From the March/April 2011 edition of Foundation Drilling:
ADSC’s Outstanding Service Award was garnered by Dr. J. Erik Loehr, University of Missouri, in acknowledgment of his research and educational efforts that advance the technical aspects of the drilled foundation and anchored earth retention industries.
Dr. Loehr is currently on the faculty of the University of Missouri and is a consultant with DBA.
By Robert Thompson, on May 9th, 2011
After some lengthy delays, the rock-socketed drilled shaft research sponsored by the Southeast Chapter of the ADSC is back on track. A second site has been selected at the site of Foundation Technologies, Inc. in Lawrenceville, Georgia. This site will investigate the resistance of some of the rocks of the Piedmont for drilled shaft design. The first test site was in Nashville, Tennessee. The report of the first test site and other information can be found at the test site page. General information about the complete project, including a list of participating/contributing companies and organizations, can be found at the project page.
Bruce Long (Long Foundation Drilling Company) is the lead for the ADSC on this project and has requested interested parties to provide comment on the test plan for the second site (see links below). The hope is to have load testing occur this July if every thing comes together properly. Bruce sent the following email with some refresher material on the Nashville test site and an update on the startup for the Lawrenceville site:
First, I would like for everyone to know that the load test program jointly planned between the Atlanta area ASCE Geotechnical community and the Southeast Chapter of the ADSC is alive and well despite some longer than planned delays. The final boring data has been in hand for some time and Dan Brown and his group have reviewed this information and submitted a preliminary load test program for review and comment. This program is very similar to the test program that was performed in Nashville a couple of years back. For informational purposes, the results of that test program has resulted in an increased awareness of the available load carrying capacity in the limestone formations in the area. Historically, shafts were designed almost exclusively utilizing end bearing with the normal range of values allowed ranging from 60-100 KSF. In recent months, we have seen projects now being designed with recommended values ranging from 100 up to 250 KSF with an increasing number of designs also relying on skin friction values up to 25 KSF in sound limestone sockets. The information gained from these load tests has given area engineers increased confidence in raising the bar for future drilled shaft designs. This will result in lower foundation costs for owners of public and private projects alike. For those involved in the design process, better information will result in improved design values and an improved competitive position for those willing to utilize this data.
Now we are prepared to move forward with the planned testing in the Atlanta area. I have attached the final geotechnical report for your review. There are several people and companies that have generously volunteered their time and expertise to make this happen, Todd Barber with Geo-Hydro Engineers, Inc. being the most notable of these. His persistence and assistance was invaluable. Others that contributed in a variety of ways include Mactec, Golder Associates, Georgia Tech and GeoTesting Express. Thanks to everyone for their efforts.
Also attached is the preliminary memo from Rob Thompson of Dan Brown and Associates. What he has outlined are suggestions based upon the boring information for two separate Osterberg Load cell tests. One would be on a shaft that was hand-cleaned, while the second shaft would be machine-cleaned only. This would allow a comparison to determine the effects (if any) that traditional hand-cleaning has on shaft behavior. This memo is being sent out with the intention that review and comments from the geotechnical community be considered and incorporated in the final program. Depending upon the extent of comments, a final meeting could be necessary to discuss any proposed revisions. If suggestions are minimal, such a meeting might not be required. In this case, we would proceed with shaft installation and testing as soon as possible.
Thanks for your patience–I think that the final results will be worth the time. It has been very rare that full scale load testing be done in hard rock areas (Piedmont or Limestone), but if the results of our Nashville area testing are any indication, I think the results will definitely show that the effort was worthwhile.
Please take time to review this information and e-mail or call me with any comments that you might have. As soon as all comments have been reviewed, we will let everyone know our plan to proceed. I would like to have comments submitted to me by May 27, 2011. If there are any questions regarding our plans, schedule, etc., please feel free to contact me at your convenience.
I have linked the proposed load test plan memo and the boring information below. Bruce would like comments from interested parties to be submitted by May 27, 2011. Please submit comments to him at blong@lfdc.com.
A blog page for this test site has been created and will be updated as the project progresses. We intend to have a prediction contest similar to the one we had for the Nashville site, so keep checking for information. Better yet, subscribe to our blog using one of the social media links at the top of the right sidebar of the blog.
Load Test Plan Memo from Dan Brown (20 May 2010)
Summary of Test Borings from GeoHydro Engineers (26 Jan 2010)
By Robert Thompson, on March 24th, 2011
Paul gave a presentation recently at the Iowa ASCE Geotechnical Conference where he discussed two project case histories for LRFD design of bridge foundations. The meeting was held March 3, 2011 in Ames, Iowa. In his presentation, Paul gave an overview of the LRFD design procedure as it applies to foundations, reminding them that LRFD is not difficult and that it provides a logical framework for incorporating reliability into foundation design. Paul talked about our experiences using LRFD for foundation design for two bridges over the Mississippi River: the Hastings Bridge in Hasting Minnesota and the new I-70 bridge in St. Louis, Missouri. Both bridges are currently under construction.
A PDF of his presentation can be found at the link through the image below, or on our Presentations page.

Previous Hastings posts
Previous I-70 posts
By Robert Thompson, on March 17th, 2011

After 5 years, Dan Brown and Associates finally has a logo! We tried to keep it simple, yet still reflect what we do best – deep foundations. That means piles, micropiles, CFA piles, as well as drilled shafts! While not necessarily the most exciting thing an engineering firm can do, it is part of growing up as a company. Hopefully you will see it more often at conferences and in publications.
By Robert Thompson, on February 1st, 2011
On December 29, 2010, Audubon Bridge Constructors recently “closed” the main span of the John James Audubon Bridge between New Roads and St. Francisville, Louisiana. Watch the video featured at the top of the page at the bridge link to hear about the bridge, including the drilled shaft foundations! For something really fascinating, go to the webcams here and scroll back through the various dates. They have archived images all the way back to start of construction.
Photo: Chris Usery, Figg Bridge Inspectors
The last cables were installed on January 3, 2011 as noted on the project website:
The last two cable stays of the longest cable-stayed bridge in the Western Hemisphere were installed on January 3, 2011, five days after the spans were connected. The John James Audubon Bridge, Louisiana’s newest crossing over the Mississippi River, now has all of its 136 cable stays in place.
This bridge will be the longest cable-stayed bridge in North America when it opens later in 2011. Again, from the project web site:
The spans of the longest cable-stayed bridge in the Western Hemisphere were connected on December 29, 2010, stretching 1/3 of a mile over the Mississippi River. The John James Audubon Bridge, connecting Pointe Coupee and West Feliciana parishes in Louisiana, is approximately 92% complete. Construction of the spans began from both sides of the 500-foot tall towers earlier this year. Both sides continue to progress at a rapid pace, and now the meeting of the spans has occurred.
Steve Dapp and I had the pleasure of working with many great people during our time on site (much more time for Steve than for me!) during foundation construction. One of them, Chris Ursery of Figg Bridge Inspectors, has been great about providing us with photos now and then to keep us updated of some of the details of the bridge construction. Chris has granted us permission to share a few of his recent photos, which are shown below or can be seen in our web albums here.
Previous post on Audubon Bridge.
By Robert Thompson, on January 27th, 2011
The Winter 2011 issue of Deep Foundations features Dan in its “People, Projects and Equipment” column. Virginia Fairweather with DFI talked to several folks in the geotechnical engineering community to learn about Dan, including yours truly. If you are interested in getting a glimpse inside the man who is Dr. Dan Brown, just check out the link below. This column is just one of many items featured in each issue of Deep Foundations, only from DFI. If you aren’t a member of DFI, then consider becoming one!
People, Projects and Equipment, Winter 2011 Deep Foundations
By Robert Thompson, on January 19th, 2011

(Image source: LakeExpo.com)
DBA is part of a team led by Parsons Transportation Group that was selected to design the replacement of the Hurricane Deck Bridge over The Lake of the Ozarks in Camden County Missouri. MoDOT has awarded the design contract to Parsons. DBA will be the lead geotechnical engineer with Terracon on the team providing drilling and laboratory services, as well as some foundation engineering support services. Parsons was chosen due to the innovative approach the team proposed that includes reusing the existing piers (from ENR.com):
MoDOT chose Parsons for proposing an innovative approach to construction that involves the use of temporary pier widening and shifting the existing superstructure over. This method will allow traffic to be maintained on the existing bridge while the new bridge is constructed, potentially resulting in significant cost savings.
A little history of the bridge can be found at Go2Lakeofthe Ozarks.com, including how it got its name:
Hurricane Deck Bridge of Ozarks crosses the main channel of the lake of approximately mile marker 35. It carries Missouri highway 5 between Versailles and Camdenton. It was built in 1936 –five years after the lake filled. It was named as Hurricane Deck because it was heard that a tornado struck that area which was locally "Hurricanes". It is a nautical term associated with river steamboats. The Hurricane Deck was the uppermost deck which provides and allows everyone to experience the pleasant breezy place and the passing scenery.
Other news links:
Lake News Online – 12/2/2010
Lake Expo.com – 12/2/2010
|
|
|