Get the New FHWA Drilled Shaft Manual
Get the NCHRP Synthesis 418 – Pile Criteria From Test Pile Data
Dan’s Speaking Schedule March 16, 2012 - "Advanced" Design and Construction Issues with Drilled Shaft Foundations; Case Histories - ADSC Equipment EXPO and Technical Conference - San Antonio, Texas
March 26-28, 2012 - State of the Art and Practice for Drilled Foundations - GeoCongress 2012 - ASCE/Geo-Institute - San Francisco, California
Other DBA Team Speaking Appearences Tim Siegel (January 22, 2012): Innovative Techniques for Characterizing Karst Terrain, Workshop on Geo-innovation in Subsurface Exploration, TRB Annual Meeting, Washington, D.C.
John Turner and Robert Thompson (February 21-23, 2012): NHI Drilled Shaft Course - Kansas DOT, Topeka, Kansas
Robert Thompson (February 24, 2012): Conservatism in Drilled Shaft Design When
Utilizing Rock Sockets, Alabama Transportation Conference, Montgomery, Alabama
Tim Siegel (March 15, 2012): Micropile Design Installation and Performance for the Foothills Parkway, ADSC Equipment EXPO and Technical Conference, San Antonio, Texas
Robert Thompson (March 15, 2012): Full-Scale Load Tests on Drilled Shafts in Tennessee and Georgia, ADSC Equipment EXPO and Technical Conference, San Antonio, Texas
Erik Loehr (March 15, 2012): Slope Stabilization Using Micropiles, ADSC Equipment EXPO and Technical Conference, San Antonio, Texas
TBA (April 10-12, 2012): NHI Drilled Shaft Course - South Carolina DOT, Columbia, South Carolina
Conferences, Meetings, Seminars, Workshops
|
Foundation Work is Finished at Audubon Bridge!!!
By Robert Thompson, on November 3rd, 2009
Yes, you read that right – the last drilled shaft has been installed on the John James Audubon Bridge near New Road, Louisiana. The project has been quite an adventure for us, especially Steve. He spent the most time on the site during shaft excavation, tip grouting, load testing, and even pile driving. Robert got to spend a fair amount of time, too, over the last couple of years. Paul was even lucky enough to make a couple of trips.
The shaft construction was concluded with one last O-cell test on Shaft 3W South. Dan was present for the last load test which went fabulously well.
If you are going to the Geo-Institute congress GeoForida 2010 next February in West Palm Beach, you can hear Steve present the paper he and Dan wrote on the tip grouting and load test program.
The bridge is still under construction, of course, and will be an awesome structure when completed. It was an exciting project for us to be a part of the team. We’ll have a project summary posted in the near future to highlight the details of the foundations. For now, you will have to be satisfied with the slideshows below (in reverse chronological order) from some of our visits this summer and fall.
Load Test at Shaft 3W South – October 2009
Excavation of Shaft 3W South – September 2009
Shaft Grouting and other Construction – June 2009
Shaft Excavation, Pile Driving, and Cofferdams – May 2009
|
|
|